23443 W HATTERAS ST 91367
Certificate Information: 23443 W HATTERAS ST 91367
- Application / Permit
- 25014-20000-02337
- Plan Check / Job No.
- B25VN12497
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 1-story covered patio addition to (E) 2-story SFD /w attached garage. Work per engineer.
- Permit Issued
- Issued on 8/27/2025
- Issuing Office
- Current Status
- CofO in Progress on 4/16/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/5/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/8/2025 | SERGIO GUTIERREZ |
| Corrections Issued | 5/23/2025 | HUAN LE |
| Quality Review Completed | 6/9/2025 | PRANITA SHAH |
| Applicant returned to address corrections | 8/4/2025 | SERGIO GUTIERREZ |
| Plan Check Approved | 8/27/2025 | SERGIO GUTIERREZ |
| Issued | 8/27/2025 | APPLICANT |
| CofO in Progress | 4/16/2026 | TROY SANDERS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/26/2025 | JEREMY CHOK |
| Grading Pre-Inspection | Cleared | 8/26/2025 | HUAN LE |
| Roof/Waste drainage to street | Cleared | 8/26/2025 | JEREMY CHOK |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Ha My Design, Inc; Lic. No.: 999603-B | , |
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: NA86051 | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 8/28/2025 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 8/28/2025 | Approved | TROY SANDERS |
| Green Building Rough | 8/28/2025 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 3/3/2026 | Approved | TROY SANDERS |
| Final | 3/3/2026 | Corrections Issued | TROY SANDERS |
| Green Building Final | 3/3/2026 | Approved | TROY SANDERS |
| HVAC-Final | 3/3/2026 | Approved | TROY SANDERS |
| PLUMBING-Final | 3/3/2026 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 3/3/2026 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 3/3/2026 | Approved | TROY SANDERS |
| Final | 4/15/2026 | OK to Issue CofO | TROY SANDERS |