11265 W MORRISON ST 91601
Certificate Information: 11265 W MORRISON ST 91601
- Application / Permit
- 25014-20000-02305
- Plan Check / Job No.
- B25VN14448
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- EPLAN.supplemental to 21016-20000-38015 to revise the work description to " Change existing (1) office and (1) Gym at second floor to (1) accessory dwelling unit (ADU) change the existing hall at the third floor to (1) accessory dwelling unit (ADU). Move the gyn to the second floor and move the leasing office to the first floor."
- Permit Issued
- Issued on 4/13/2026
- Issuing Office
- Current Status
- Issued on 4/13/2026
Permit Application Status History
| Submitted | 5/22/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/5/2025 | ARSALAN SHABESTARI |
| Assigned to Zoning Architect | 6/5/2025 | MEGAN KOLP |
| Corrections Issued | 6/10/2025 | ARSALAN SHABESTARI |
| Quality Review Completed | 6/13/2025 | SINA KHOSRAVI |
| Applicant returned to address corrections | 12/13/2025 | ARSALAN SHABESTARI |
| Plan Check Approved | 4/1/2026 | ARSALAN SHABESTARI |
| Issued | 4/13/2026 | APPLICANT |
Permit Application Clearance Information
| DAS Clearance | Cleared | 6/9/2025 | Chad Doi |
| Green Code | Cleared | 6/10/2025 | MICHAEL AYERS |
| Address approval | Cleared | 7/11/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 7/11/2025 | RYAN CASTRO |
| Tenant Habitability Plan | Cleared | 11/21/2025 | KORNEL LELEA |
| CPC | Cleared | 12/1/2025 | JAZMIN ROQUE |
| Eng Process Fee Ord 176,300 | Cleared | 12/13/2025 | JEREMY CHOK |
| Fire Marshal Fire Life Safety | Cleared | 2/11/2026 | FIRE DEPARTMENT |
| Zoning Plan Check | Cleared | 3/10/2026 | MEGAN KOLP |
Contact Information
| Contractor | California Designers Remodeling Inc; Lic. No.: 946160-B | , |
| Engineer | Ni,, Zhang Yuan; Lic. No.: NA68149 | , |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 4/22/2026 | Corrections Issued | JEFFREY FULTON |
| Wood Frame | 4/24/2026 | Partial Inspection | JEFFREY FULTON |
| Drywall Nailing | 4/27/2026 | Partial Inspection | JEFFREY FULTON |
| Drywall Nailing | 5/1/2026 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Drywall Nailing | 5/4/2026 | Partial Approval | DEANDRE HOFFMAN |