24324 W FRIAR ST 91367

Certificate Information: 24324 W FRIAR ST 91367

Application / Permit
25014-20000-02299
Plan Check / Job No.
B25VN14415
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan Addition of 750 sf to (E) SFD W/attached garage. Per engineering design.
Permit Issued
Issued on 7/8/2025
Issuing Office
Current Status
CofO Issued on 6/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/21/2025 APPLICANT
Assigned to Plan Check Engineer 5/23/2025 ALFREDO JARA
Corrections Issued 5/24/2025 ALFREDO JARA
Applicant returned to address corrections 6/12/2025 ALFREDO JARA
Plan Check Approved 6/16/2025 ALFREDO JARA
Plan Check Approved 6/23/2025 ALFREDO JARA
Issued 7/8/2025 APPLICANT
CofO in Progress 6/4/2026 GEVORK IPCHYAN
Permit Finaled 6/11/2026 JOHN JANSON
CofO Issued 6/11/2026 JOHN JANSON
Permit Finaled 6/11/2026 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/5/2025 RYAN CASTRO
Watercourse Cleared 6/5/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 6/9/2025 RYAN CASTRO

Contact Information

Architect Chopra,, Romesh K; Lic. No.: NA9900       ,
Contractor Jlemos Builders Inc; Lic. No.: 1098171-B       ,
Engineer Zakeri,, Behzad; Lic. No.: C89670 13628 FREEPORT RD      SAN DIEGO, CA 92129
Engineer Zakeri,, Behzad; Lic. No.: NA89670       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/10/2025 Approved GEVORK IPCHYAN
Deputy Drilled-In Anchors 8/25/2025 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 9/4/2025 Approved TROY SANDERS
PLUMBING-Rough 9/4/2025 Partial Approval TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 11/12/2025 Partial Approval GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 12/19/2025 Approved GEVORK IPCHYAN
PLUMBING-Rough 12/19/2025 Partial Approval GEVORK IPCHYAN
Shower Pan 12/19/2025 Approved GEVORK IPCHYAN
BUILDING-Rough-Frame 1/13/2026 Partial Approval GEVORK IPCHYAN
ELECTRICAL-Rough 1/13/2026 Not Ready for Inspection GEVORK IPCHYAN
Green Building Rough 1/13/2026 Approved GEVORK IPCHYAN
HVAC-Rough 1/13/2026 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 1/13/2026 Partial Approval GEVORK IPCHYAN
PLUMBING-Rough 1/13/2026 Corrections Issued GEVORK IPCHYAN
BUILDING-Rough-Frame 1/20/2026 Approved GEVORK IPCHYAN
ELECTRICAL-Rough 1/20/2026 Approved GEVORK IPCHYAN
Gas Test 1/20/2026 Approved GEVORK IPCHYAN
Green Building Rough 1/20/2026 Approved GEVORK IPCHYAN
Insulation 1/20/2026 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 1/20/2026 Partial Approval GEVORK IPCHYAN
PLUMBING-Rough 1/20/2026 Approved GEVORK IPCHYAN
Drywall Nailing 1/26/2026 Approved GEVORK IPCHYAN
ELECTRICAL-Final 5/21/2026 Approved GEVORK IPCHYAN
HVAC-Final 5/21/2026 Approved GEVORK IPCHYAN
PLUMBING-Final 5/21/2026 Approved GEVORK IPCHYAN
Service/Power Release 5/21/2026 Approved GEVORK IPCHYAN
Final 6/3/2026 OK to Issue CofO GEVORK IPCHYAN
Green Building Final 6/3/2026 Approved GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 6/3/2026 SGSOV Approved GEVORK IPCHYAN
Smoke Detectors 6/3/2026 Approved GEVORK IPCHYAN