144 1/2 W 49TH ST 90037

Certificate Information: 144 1/2 W 49TH ST 90037

Application / Permit
25014-20000-02291
Plan Check / Job No.
B25VN14380
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: CONVERT (E) RECREATION ROOM (197 SF) TO DETACHED A.D.U. AND SHOWER ADDITION (12.5 SF) PER STATE LAW
Permit Issued
Issued on 10/2/2025
Issuing Office
Current Status
Issued on 10/2/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/22/2025 APPLICANT
Assigned to Plan Check Engineer 5/28/2025 NEHEMIAS RAMOS
Corrections Issued 5/29/2025 NEHEMIAS RAMOS
Applicant returned to address corrections 8/16/2025 LAWRENCE QUIRANTE
Applicant returned to address corrections 8/22/2025 NEHEMIAS RAMOS
Applicant returned to address corrections 9/10/2025 LAWRENCE QUIRANTE
Plan Check Approved 9/11/2025 NEHEMIAS RAMOS
Issued 10/2/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/12/2025 JEREMY CHOK
Sewer availability Cleared 7/12/2025 JEREMY CHOK
Eng Process Fee Ord 176,300 Cleared 7/21/2025 JEREMY CHOK
Construction near power lines Cleared 8/4/2025 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/14/2025 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 11/14/2025 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 11/18/2025 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 11/18/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 12/10/2025 Approved ALEJANDRO DE ARTOLA
Shower Pan 12/10/2025 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 12/11/2025 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 12/11/2025 Partial Approval ALEJANDRO DE ARTOLA
Insulation 12/11/2025 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 12/12/2025 Approved ANTHONY RAMOS
ELECTRICAL-Final 2/9/2026 Corrections Issued ALEJANDRO DE ARTOLA
Final 2/9/2026 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 2/9/2026 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 2/9/2026 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 4/27/2026 Corrections Issued ALEJANDRO DE ARTOLA
Final 4/27/2026 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 4/27/2026 Corrections Issued ALEJANDRO DE ARTOLA