4501 N CANOGA DR 91364
Certificate Information: 4501 N CANOGA DR 91364
- Application / Permit
- 25014-20000-02279
- Plan Check / Job No.
- B25VN14309
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL & IRR. SHAPED ADDITION AT FRONT AND REAR (884 SF) OF (E) ONE STORY SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE;
- Permit Issued
- Issued on 9/3/2025
- Issuing Office
- Valley
- Current Status
- Issued on 9/3/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/21/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/12/2025 | SEAN SHAHMIRI |
| Corrections Issued | 6/18/2025 | SEAN SHAHMIRI |
| Quality Review Completed | 6/18/2025 | STEVEN KIM |
| Building Plans Picked Up | 6/20/2025 | APPLICANT |
| Plan Check Approved | 8/27/2025 | SEAN SHAHMIRI |
| Issued | 9/3/2025 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 6/26/2025 | JESUS CISNEROS |
| BHO/Hillside ordinance | Cleared | 6/26/2025 | JESUS CISNEROS |
| BHO/Hillside ordinance | Cleared | 6/26/2025 | JESUS CISNEROS |
| BHO/Hillside ordinance | Cleared | 6/26/2025 | JESUS CISNEROS |
| BHO/Hillside ordinance | Cleared | 6/26/2025 | JESUS CISNEROS |
| Sewer availability | Cleared | 6/26/2025 | JESUS CISNEROS |
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2025 | JESUS CISNEROS |
| Grading Pre-Inspection | Cleared | 7/17/2025 | GERMAN RODRIGUEZ MENDOZA |
| Specific Plan | Cleared | 7/22/2025 | TIFFANY CORRALES |
| Specific Plan | Cleared | 7/22/2025 | TIFFANY CORRALES |
| Hydrant and Access approval | Cleared | 8/6/2025 | JERRY KAO |
| Roof/Waste drainage to street | Cleared | 8/27/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Moallem Nabiollah N; Lic. No.: 643280-B | 5333 BALBOA BLVD 218 ENCINO, CA 91316 |
| Engineer | Mirzadeh,, Amir; Lic. No.: C58119 | P O BOX 572110 TARZANA, CA 91357 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/10/2025 | Conditional Approval | JOHN HAYES |
| Special/Order Compliance | 9/15/2025 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 9/23/2025 | Corrections Issued | JOHN HAYES |
| Underground Mechanical | 9/23/2025 | Partial Approval | JOHN HAYES |
| Footing/Foundation/Slab | 9/25/2025 | Approved | JOHN KIDWELL |
| Underground Mechanical | 9/25/2025 | Partial Approval | JOHN KIDWELL |
| Service/Power Release | 10/30/2025 | Partial Inspection | KRISTEN CAUSEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/26/2025 | Corrections Issued | JOHN HAYES |
| Deputy Wood Construction | 12/30/2025 | Conditional Approval | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2026 | Partial Approval | JOHN HAYES |
| Wood Frame | 1/7/2026 | Partial Approval | JOHN HAYES |
| ELECTRICAL-Rough | 3/26/2026 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2026 | Partial Approval | SEAN WIRCH |
| HVAC-Rough | 3/26/2026 | Approved | SEAN WIRCH |
| PLUMBING-Rough | 3/26/2026 | Approved | SEAN WIRCH |
| BUILDING-Rough-Frame | 4/8/2026 | Approved | JOHN HAYES |
| Green Building Rough | 4/8/2026 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 4/8/2026 | Partial Approval | JOHN HAYES |
| Insulation | 4/17/2026 | Approved | JOHN HAYES |
| Drywall Nailing | 4/27/2026 | Approved | JEFFREY HARTLINE |