5945 N TOBIAS AVE 91411
Certificate Information: 5945 N TOBIAS AVE 91411
- Application / Permit
- 25014-20000-02235
- Plan Check / Job No.
- B25VN14065
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED IRR SHAPED ADDITION & REMODEL W/ ALL NEW WINDOWS, DOORS & ENTIRELY NEW FLAT ROOF FRAMING. <NFPA-13D FIRE SPRINKLER THRU-OUT>
- Permit Issued
- Issued on 6/3/2025
- Issuing Office
- Current Status
- Issued on 6/3/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/19/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2025 | HAYATO TSUCHIYA |
| Corrections Issued | 5/29/2025 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 5/29/2025 | APPLICANT |
| Plan Check Approved | 6/3/2025 | ISIS ARGUETA |
| Issued | 6/3/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/27/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 5/27/2025 | LEE GUILBEAUX |
| ZA Case | Cleared | 5/27/2025 | JASON CHAN |
| Public Works-Highway Ded. | Cleared | 5/27/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 5/28/2025 | LEE GUILBEAUX |
Contact Information
| Architect | Callan,, Katsiaryna; Lic. No.: C40984 | 8969 LA DONA CT FOUNTAIN VALLEY, CA 92708 |
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/20/2025 | Partial Inspection | RYAN SALAZAR |
| Footing/Foundation/Slab | 7/1/2025 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 7/25/2025 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 7/30/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 7/30/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2025 | Partial Approval | RYAN SALAZAR |
| Deputy Wood Construction | 8/14/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Green Building Rough | 8/25/2025 | Approved | RYAN SALAZAR |
| HVAC-Rough | 8/25/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Insulation | 8/25/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Interior/Exterior Lathing | 8/25/2025 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 8/25/2025 | Not Ready for Inspection | RYAN SALAZAR |
| BUILDING-Rough-Frame | 8/28/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Green Building Final | 8/28/2025 | Order to Comply Issued | WAYNE REGESTER |
| HVAC-Rough | 8/28/2025 | Corrections Issued | WAYNE REGESTER |
| PLUMBING-Rough | 8/28/2025 | Approved | WAYNE REGESTER |
| BUILDING-Rough-Frame | 9/8/2025 | Approved | RYAN SALAZAR |
| HVAC-Rough | 9/8/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 9/8/2025 | Approved | RYAN SALAZAR |
| Insulation | 9/12/2025 | Approved | RYAN SALAZAR |
| Drywall Nailing | 9/26/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 11/17/2025 | Approved | CHRISTOPHER MORFIN |