5945 N TOBIAS AVE 91411

Certificate Information: 5945 N TOBIAS AVE 91411

Application / Permit
25014-20000-02235
Plan Check / Job No.
B25VN14065
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED IRR SHAPED ADDITION & REMODEL W/ ALL NEW WINDOWS, DOORS & ENTIRELY NEW FLAT ROOF FRAMING. <NFPA-13D FIRE SPRINKLER THRU-OUT>
Permit Issued
Issued on 6/3/2025
Issuing Office
Current Status
Issued on 6/3/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/19/2025 APPLICANT
Assigned to Plan Check Engineer 5/23/2025 HAYATO TSUCHIYA
Corrections Issued 5/29/2025 HAYATO TSUCHIYA
Building Plans Picked Up 5/29/2025 APPLICANT
Plan Check Approved 6/3/2025 ISIS ARGUETA
Issued 6/3/2025 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/27/2025 LEE GUILBEAUX
Sewer availability Cleared 5/27/2025 LEE GUILBEAUX
ZA Case Cleared 5/27/2025 JASON CHAN
Public Works-Highway Ded. Cleared 5/27/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 5/28/2025 LEE GUILBEAUX

Contact Information

Architect Callan,, Katsiaryna; Lic. No.: C40984 8969 LA DONA CT      FOUNTAIN VALLEY, CA 92708
Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/20/2025 Partial Inspection RYAN SALAZAR
Footing/Foundation/Slab 7/1/2025 Approved MATTHEW NELSON
ELECTRICAL-Rough 7/25/2025 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 7/30/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Gas Test 7/30/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 7/30/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 8/12/2025 Partial Approval RYAN SALAZAR
Deputy Wood Construction 8/14/2025 Conditional Approval JOAQUIN GREENOUGH
Green Building Rough 8/25/2025 Approved RYAN SALAZAR
HVAC-Rough 8/25/2025 Not Ready for Inspection RYAN SALAZAR
Insulation 8/25/2025 Not Ready for Inspection RYAN SALAZAR
Interior/Exterior Lathing 8/25/2025 Partial Approval RYAN SALAZAR
PLUMBING-Rough 8/25/2025 Not Ready for Inspection RYAN SALAZAR
BUILDING-Rough-Frame 8/28/2025 Not Ready for Inspection WAYNE REGESTER
Green Building Final 8/28/2025 Order to Comply Issued WAYNE REGESTER
HVAC-Rough 8/28/2025 Corrections Issued WAYNE REGESTER
PLUMBING-Rough 8/28/2025 Approved WAYNE REGESTER
BUILDING-Rough-Frame 9/8/2025 Approved RYAN SALAZAR
HVAC-Rough 9/8/2025 Approved RYAN SALAZAR
PLUMBING-Rough 9/8/2025 Approved RYAN SALAZAR
Insulation 9/12/2025 Approved RYAN SALAZAR
Drywall Nailing 9/26/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 11/17/2025 Approved CHRISTOPHER MORFIN