9800 N SHOSHONE AVE 91325

Certificate Information: 9800 N SHOSHONE AVE 91325

Application / Permit
25014-20000-02216
Plan Check / Job No.
B25VN13918
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN- (N) ADDITION TO EXISTING SFD TO ENLARGE EXISTING BATHROOM.
Permit Issued
Issued on 8/19/2025
Issuing Office
Current Status
CofO Issued on 5/14/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/19/2025 APPLICANT
Assigned to Plan Check Engineer 5/23/2025 ARAMIK SHAHMIRZAIAN
Corrections Issued 5/27/2025 ARAMIK SHAHMIRZAIAN
Applicant returned to address corrections 7/3/2025 ARAMIK SHAHMIRZAIAN
Applicant returned to address corrections 7/16/2025 KAMYAR EMAMI
Plan Check Approved 7/24/2025 ARAMIK SHAHMIRZAIAN
No Progress 8/7/2025 ARAMIK SHAHMIRZAIAN
Plan Check Approved 8/7/2025 ARAMIK SHAHMIRZAIAN
Issued 8/19/2025 APPLICANT
No Progress 4/8/2026 CHRISTOPHER ROJAS
CofO in Progress 4/8/2026 CHRISTOPHER ROJAS
CofO in Progress 5/5/2026 JOSE AVILA
CofO Issued 5/14/2026 RUBEN SALAS
Permit Finaled 5/14/2026 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/15/2025 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 6/17/2025 MICHAEL BROWN
Grading Pre-Inspection Cleared 6/24/2025 ALEXANDER HELFER

Contact Information

Contractor Parker Bldg & Concrete; Lic. No.: 744777-B       ,
Engineer Espino,, Manuel A; Lic. No.: NA55526       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/27/2025 Corrections Issued NICHOLAS TROWBRIDGE
Deputy Drilled-In Anchors 9/12/2025 Conditional Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 9/17/2025 Approved NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 10/22/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Rough 10/22/2025 Approved NICHOLAS TROWBRIDGE
Rough-Elec/Plmb/HVAC 10/22/2025 Approved NICHOLAS TROWBRIDGE
Shower Pan 11/21/2025 Approved KEVIN BERBERYAN
Drywall Nailing 12/23/2025 Corrections Issued JENNIFER RABUCHIN
Drywall Nailing 1/13/2026 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 2/3/2026 Approved KEVIN BERBERYAN
Final 3/26/2026 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 3/26/2026 Approved KEVIN BERBERYAN
Smoke Detectors 3/26/2026 Approved KEVIN BERBERYAN
Final 4/6/2026 OK to Issue CofO DAVID MATSON
Final 4/8/2026 Partial Inspection CHRISTOPHER ROJAS