20606 W CLARENDON ST 91367
Certificate Information: 20606 W CLARENDON ST 91367
- Application / Permit
- 25014-20000-02214
- Plan Check / Job No.
- B25VN13901
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL, REMOVE (E) CARPORT, 21'-5" X 20'-6" ADDITION W/ 20'-0" X 21'-0" TWO CAR GARAGE AT FRONT, 31'-9" X 28'-9" (IRREGULAR SHAPED) ADDITON W/PATIO AT REAR OF SFD. FIRE SPRINKLER (NFPA-13D) IS REQUIRED THROUGHOUT.
- Permit Issued
- Issued on 8/11/2025
- Issuing Office
- Current Status
- Issued on 8/11/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/21/2025 | ARTIN ZARUKIAN |
| Corrections Issued | 5/24/2025 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 5/28/2025 | APPLICANT |
| Plan Check Approved | 7/3/2025 | NAREG ATARIAN |
| Plan Check Approved | 7/3/2025 | GURUNATH NESARAJAH |
| Issued | 8/11/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/10/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 6/10/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 6/10/2025 | BIAINA HARITUNIAN |
| GPI Written Notices | Cleared | 7/3/2025 | MANUEL TEJADA |
| Grading Pre-Inspection | Cleared | 7/3/2025 | MANUEL TEJADA |
Contact Information
| Contractor | Alpha One Construction Inc; Lic. No.: 1010086-B | 5827 FRANKLIN AVE LOS ANGELES, CA 90028 |
| Engineer | Mosesian,, Peter; Lic. No.: C95745 | 86 SMOKE TREE AVE OAK PARK, CA 91377 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Drywall Nailing | 7/24/2026 |
| Pre-Inspection | 7/28/2026 |
Inspection Request History
| Pre-Inspection | 8/14/2025 | No Access for Inspection | ALEXANDER HANDY |
| Excavation/Setback/Form/Re-Bar | 11/7/2025 | Corrections Issued | ROBERT GOLD |
| PLUMBING-Rough | 11/7/2025 | Corrections Issued | ROBERT GOLD |
| PLUMBING-Rough | 11/12/2025 | Partial Approval | JUAN ALVARADO |
| Deputy Drilled-In Anchors | 1/16/2026 | Conditional Approval | ALEXANDER HANDY |
| Footing/Foundation/Slab | 1/20/2026 | Corrections Issued | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 1/22/2026 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 3/10/2026 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Rough | 3/10/2026 | Not Ready for Inspection | ALEXANDER HANDY |
| PLUMBING-Rough | 5/7/2026 | Corrections Issued | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2026 | Not Ready for Inspection | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2026 | Corrections Issued | ALEXANDER HANDY |
| HVAC-Rough | 6/3/2026 | Corrections Issued | ALEXANDER HANDY |
| Deputy Wood Construction | 6/4/2026 | Conditional Approval | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2026 | Partial Approval | ALEXANDER HANDY |
| HVAC-Rough | 6/16/2026 | Not Ready for Inspection | ALEXANDER HANDY |
| Pre-Inspection | 6/16/2026 | Partial Inspection | ALEXANDER HANDY |
| Shower Pan | 6/16/2026 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Rough | 7/7/2026 | Partial Approval | ROBERT GOLD |
| Interior/Exterior Lathing | 7/7/2026 | Partial Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 7/10/2026 | Not Ready for Inspection | ALEXANDER HANDY |
| Interior/Exterior Lathing | 7/10/2026 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 7/16/2026 | Partial Approval | ALEXANDER HANDY |
| Green Building Rough | 7/16/2026 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 7/16/2026 | Approved | ALEXANDER HANDY |
| Insulation | 7/21/2026 | No Result Entered | ALEXANDER HANDY |