8514 N HATILLO AVE 91306

Certificate Information: 8514 N HATILLO AVE 91306

Application / Permit
25014-20000-02147
Plan Check / Job No.
B25VN13473
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO EXISTING 1 STORY SFD
Permit Issued
Issued on 6/9/2025
Issuing Office
Current Status
Issued on 6/9/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/14/2025 APPLICANT
Assigned to Plan Check Engineer 5/19/2025 CRYSTEL MAALOUF
Corrections Issued 5/20/2025 CRYSTEL MAALOUF
Applicant returned to address corrections 5/29/2025 SHANGQIN XIE
Plan Check Approved 6/4/2025 CARLOS MONTES
Issued 6/9/2025 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/30/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 6/2/2025 SAFA JAVANMARDI
Sewer availability Cleared 6/2/2025 SAFA JAVANMARDI

Contact Information

Architect Hanna,, Remon; Lic. No.: C36271 26030 SANDBURG PL      STEVENSON RANCH, CA 91381
Contractor Owner-Builder       ,
Engineer Abdel, Messih, Raymond; Lic. No.: C79913 23216 CICELY CT      VALENCIA, CA 91354

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/3/2025 Conditional Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 7/11/2025 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 8/12/2025 Partial Approval JEFFREY HARTLINE
PLUMBING-Rough 8/12/2025 Partial Approval JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 8/15/2025 Partial Approval JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 9/10/2025 Partial Approval JEFFREY HARTLINE
Deputy Drilled-In Anchors 9/25/2025 Conditional Approval JEFFREY HARTLINE
ELECTRICAL-Rough 12/1/2025 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 12/1/2025 Partial Approval JEFFREY HARTLINE
PLUMBING-Rough 12/1/2025 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 12/9/2025 Approved JEFFREY HARTLINE
Green Building Rough 12/9/2025 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 12/9/2025 Partial Approval JEFFREY HARTLINE
Insulation 12/18/2025 Approved CHRIS CHRISTENSEN
Drywall Nailing 12/24/2025 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 1/21/2026 Partial Approval JEFFREY HARTLINE
Shower Pan 1/21/2026 Approved JEFFREY HARTLINE