9512 N DORRINGTON AVE 91331
Certificate Information: 9512 N DORRINGTON AVE 91331
- Application / Permit
- 25014-20000-02142
- Plan Check / Job No.
- B25VN13454
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. ADDITION TO GARAGE TO CREATE ADU WITH ATTACHED GARAGE PER ORDIANCE
- Permit Issued
- Issued on 10/15/2025
- Issuing Office
- Current Status
- CofO Issued on 6/5/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/19/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2025 | NEHEMIAS RAMOS |
| Corrections Issued | 5/24/2025 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 7/16/2025 | EDWIN MARTINEZ |
| Applicant returned to address corrections | 9/19/2025 | NEHEMIAS RAMOS |
| Plan Check Approved | 10/14/2025 | NEHEMIAS RAMOS |
| Issued | 10/15/2025 | APPLICANT |
| CofO in Progress | 5/19/2026 | MICHEL ABAJAN |
| Permit Finaled | 6/5/2026 | RUBEN SALAS |
| CofO Issued | 6/5/2026 | RUBEN SALAS |
| Permit Finaled | 6/5/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/1/2025 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 8/1/2025 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/19/2025 | DAVID LOPEZ |
| Sewer availability | Cleared | 9/19/2025 | DAVID LOPEZ |
| Construction near power lines | Cleared | 10/9/2025 | GEVORK KARAPETYAN |
| Construction within easement | Cleared | 10/9/2025 | GEVORK KARAPETYAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/5/2025 | Corrections Issued | MICHEL ABAJAN |
| Footing/Foundation/Slab | 12/5/2025 | Corrections Issued | MICHEL ABAJAN |
| Sewer | 12/5/2025 | Approved | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 12/11/2025 | Conditional Approval | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 12/15/2025 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 12/15/2025 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 12/30/2025 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Rough | 12/30/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 1/14/2026 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 1/14/2026 | Approved | MICHEL ABAJAN |
| Green Building Rough | 1/14/2026 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 1/14/2026 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 1/14/2026 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 1/14/2026 | Approved | MICHEL ABAJAN |
| Insulation | 1/20/2026 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 1/26/2026 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 4/21/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 4/21/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 4/21/2026 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 4/21/2026 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 4/21/2026 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 5/8/2026 | Approved | MICHEL ABAJAN |
| Final | 5/8/2026 | Corrections Issued | MICHEL ABAJAN |
| HVAC-Final | 5/8/2026 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Final | 5/8/2026 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 5/8/2026 | SGSOV Approved | MICHEL ABAJAN |
| Final | 5/18/2026 | OK to Issue CofO | MICHEL ABAJAN |