9512 N DORRINGTON AVE 91331

Certificate Information: 9512 N DORRINGTON AVE 91331

Application / Permit
25014-20000-02142
Plan Check / Job No.
B25VN13454
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. ADDITION TO GARAGE TO CREATE ADU WITH ATTACHED GARAGE PER ORDIANCE
Permit Issued
Issued on 10/15/2025
Issuing Office
Current Status
CofO Issued on 6/5/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/19/2025 APPLICANT
Assigned to Plan Check Engineer 5/23/2025 NEHEMIAS RAMOS
Corrections Issued 5/24/2025 NEHEMIAS RAMOS
Applicant returned to address corrections 7/16/2025 EDWIN MARTINEZ
Applicant returned to address corrections 9/19/2025 NEHEMIAS RAMOS
Plan Check Approved 10/14/2025 NEHEMIAS RAMOS
Issued 10/15/2025 APPLICANT
CofO in Progress 5/19/2026 MICHEL ABAJAN
Permit Finaled 6/5/2026 RUBEN SALAS
CofO Issued 6/5/2026 RUBEN SALAS
Permit Finaled 6/5/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/1/2025 DAVID LOPEZ
Roof/Waste drainage to street Cleared 8/1/2025 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 9/19/2025 DAVID LOPEZ
Sewer availability Cleared 9/19/2025 DAVID LOPEZ
Construction near power lines Cleared 10/9/2025 GEVORK KARAPETYAN
Construction within easement Cleared 10/9/2025 GEVORK KARAPETYAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/5/2025 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 12/5/2025 Corrections Issued MICHEL ABAJAN
Sewer 12/5/2025 Approved MICHEL ABAJAN
Deputy Drilled-In Anchors 12/11/2025 Conditional Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 12/15/2025 Approved MICHEL ABAJAN
Footing/Foundation/Slab 12/15/2025 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 12/30/2025 Corrections Issued KEVIN BERBERYAN
Green Building Rough 12/30/2025 Not Ready for Inspection KEVIN BERBERYAN
BUILDING-Rough-Frame 1/14/2026 Approved MICHEL ABAJAN
ELECTRICAL-Rough 1/14/2026 Approved MICHEL ABAJAN
Green Building Rough 1/14/2026 Approved MICHEL ABAJAN
HVAC-Rough 1/14/2026 Approved MICHEL ABAJAN
Interior/Exterior Lathing 1/14/2026 Approved MICHEL ABAJAN
PLUMBING-Rough 1/14/2026 Approved MICHEL ABAJAN
Insulation 1/20/2026 Approved MICHEL ABAJAN
Drywall Nailing 1/26/2026 Approved MICHEL ABAJAN
ELECTRICAL-Final 4/21/2026 Corrections Issued JENNIFER RABUCHIN
Final 4/21/2026 Corrections Issued JENNIFER RABUCHIN
Green Building Final 4/21/2026 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 4/21/2026 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 4/21/2026 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 5/8/2026 Approved MICHEL ABAJAN
Final 5/8/2026 Corrections Issued MICHEL ABAJAN
HVAC-Final 5/8/2026 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Final 5/8/2026 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 5/8/2026 SGSOV Approved MICHEL ABAJAN
Final 5/18/2026 OK to Issue CofO MICHEL ABAJAN