10426 S GRAMERCY PL 90047

Certificate Information: 10426 S GRAMERCY PL 90047

Application / Permit
25014-20000-02136
Plan Check / Job No.
B25VN13435
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY (30' X 20') ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1)
Permit Issued
Issued on 1/12/2026
Issuing Office
Valley
Current Status
Issued on 1/12/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/13/2025 APPLICANT
Assigned to Plan Check Engineer 5/15/2025 VAHAN JIVALAGIAN
Corrections Issued 5/29/2025 VAHAN JIVALAGIAN
Quality Review Completed 5/29/2025 OMID HEDAYAT
Building Plans Picked Up 6/5/2025 APPLICANT
Plan Check Approved 12/17/2025 VAHAN JIVALAGIAN
Issued 1/12/2026 APPLICANT

Permit Application Clearance Information

Hold Cleared 9/15/2025 MARIA VENDIVIL
Address approval Cleared 9/19/2025 DAVID LOPEZ
Roof/Waste drainage to street Cleared 9/19/2025 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 11/6/2025 DAVID LOPEZ
Sewer availability Cleared 11/6/2025 DAVID LOPEZ
Construction near power lines Cleared 11/12/2025 EDGAR PASCUA
Hold Cleared 1/30/2026 CARMEN MERAZ

Contact Information

Contractor Balcantara Construction Inc; Lic. No.: 1137061-B 44637 CERISA STREET      LANCASTER, CA 93535
Engineer Garcia,, Eddy Alexander; Lic. No.: S6159 17958 LULL ST      RESEDA, CA 91335

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Floor/Roof Diaphrgm/Shear Wall 6/12/2026    Time Frame: 9-11
ELECTRICAL-Rough 6/12/2026    Time Frame: 9-11

Inspection Request History

Footing/Foundation/Slab 2/4/2026 Corrections Issued SALVADOR MARTINEZ
METHANE-Barrier 2/4/2026 Approved SALVADOR MARTINEZ
METHANE-Subgrade 2/4/2026 Approved SALVADOR MARTINEZ
Sewer 2/4/2026 Partial Approval SALVADOR MARTINEZ
Special/Order Compliance 2/4/2026 Corrections Issued SALVADOR MARTINEZ
Underground Mechanical 2/4/2026 Partial Approval SALVADOR MARTINEZ
Footing/Foundation/Slab 2/10/2026 Approved SALVADOR MARTINEZ
Sewer 2/10/2026 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 3/2/2026 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 3/2/2026 Corrections Issued SALVADOR MARTINEZ
BUILDING-Rough-Frame 3/3/2026 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 3/3/2026 Partial Approval SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 3/4/2026 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 4/27/2026 Corrections Issued SALVADOR MARTINEZ
HVAC-Rough 4/27/2026 Corrections Issued SALVADOR MARTINEZ
Deputy Wood Construction 5/13/2026 Conditional Approval ALEX COLIN
HVAC-Rough 6/11/2026 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 6/11/2026 Partial Inspection SALVADOR MARTINEZ