14601-14603 W LABRADOR ST 91402

Certificate Information: 14601-14603 W LABRADOR ST 91402

Application / Permit
25014-20000-02114
Plan Check / Job No.
B25VN13267
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. CONVERT (E) Attached GARAGE TO (N) ACCESSORY DWELLING UNIT (350 SQFT) Per State law. Work per engineer design.
Permit Issued
Issued on 9/18/2025
Issuing Office
Current Status
CofO Issued on 2/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/12/2025 APPLICANT
Assigned to Plan Check Engineer 5/15/2025 EDWIN MARTINEZ
Corrections Issued 5/16/2025 EDWIN MARTINEZ
Plan Check Approved 5/29/2025 EDWIN MARTINEZ
Issued 9/18/2025 APPLICANT
CofO in Progress 2/4/2026 MATTHEW NELSON
Permit Finaled 2/26/2026 RUBEN SALAS
CofO Issued 2/26/2026 RUBEN SALAS
Permit Finaled 2/26/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/20/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 5/20/2025 LEE GUILBEAUX
Sewer availability Cleared 5/20/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 5/20/2025 LEE GUILBEAUX

Contact Information

Contractor No Limit Design And Build Llc; Lic. No.: 1117243-B       ,
Engineer Wu,, Shu; Lic. No.: NA90391       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/22/2025 Corrections Issued JENNIFER RABUCHIN
Pre-Inspection 9/22/2025 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 9/25/2025 Approved JENNIFER RABUCHIN
Rough-Elec/Plmb/HVAC 9/25/2025 Not Ready for Inspection JENNIFER RABUCHIN
Underground Mechanical 9/25/2025 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 9/29/2025 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 10/1/2025 Corrections Issued JENNIFER RABUCHIN
METHANE-Rough 10/1/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 10/3/2025 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 10/3/2025 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 10/3/2025 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 10/8/2025 Corrections Issued JENNIFER RABUCHIN
Deputy Wood Construction 10/8/2025 Conditional Approval RAUL OLAGI
ELECTRICAL-Rough 10/8/2025 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 10/8/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 10/8/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 10/9/2025 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 10/15/2025 Corrections Issued NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 10/17/2025 Corrections Issued JENNIFER RABUCHIN
Insulation 10/22/2025 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 10/22/2025 Partial Approval JENNIFER RABUCHIN
Drywall Nailing 10/27/2025 Partial Approval JENNIFER RABUCHIN
Drywall Nailing 10/28/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 11/13/2025 No Access for Inspection JENNIFER RABUCHIN
HVAC-Rough 11/13/2025 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 11/17/2025 Approved JENNIFER RABUCHIN
Shower Pan 12/10/2025 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 12/17/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 12/17/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/29/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 12/29/2025 Corrections Issued JENNIFER RABUCHIN
Final 12/29/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 12/29/2025 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 12/29/2025 SGSOV Not Ready JENNIFER RABUCHIN
Service/Power Release 12/29/2025 Not Required JENNIFER RABUCHIN
Smoke Detectors 12/29/2025 Corrections Issued JENNIFER RABUCHIN
Final 2/3/2026 OK to Issue CofO MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 2/3/2026 SGSOV Approved MATTHEW NELSON
Smoke Detectors 2/3/2026 Approved MATTHEW NELSON