10155 N MT GLEASON AVE 91040

Certificate Information: 10155 N MT GLEASON AVE 91040

Application / Permit
25014-20000-02095
Plan Check / Job No.
B25VN13165
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: REMODEL TO EXISTING SINGLE FAMILY DWELLING AND (24'-2" X 16'-5" IRR SHAPE) ADDITION
Permit Issued
Issued on 7/14/2025
Issuing Office
Current Status
CofO Issued on 3/12/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/9/2025 APPLICANT
Assigned to Plan Check Engineer 5/15/2025 VAHAN JIVALAGIAN
Corrections Issued 5/18/2025 VAHAN JIVALAGIAN
Quality Review Completed 5/22/2025 OMID HEDAYAT
Applicant returned to address corrections 6/26/2025 VAHAN JIVALAGIAN
Plan Check Approved 7/13/2025 VAHAN JIVALAGIAN
Issued 7/14/2025 APPLICANT
CofO in Progress 2/5/2026 DAVID ANDERSON
Permit Finaled 3/12/2026 RUBEN SALAS
CofO Issued 3/12/2026 RUBEN SALAS
Permit Finaled 3/12/2026 RUBEN SALAS

Permit Application Clearance Information

Hydrant and Access approval Cleared 6/2/2025 GILBERT URREA
Roof/Waste drainage to street Cleared 6/3/2025 WALLIE JONG
Sewer availability Cleared 6/3/2025 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 6/5/2025 WALLIE JONG
Grading Pre-Inspection Cleared 6/26/2025 VAHAN JIVALAGIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Ursu,, Dragos; Lic. No.: C79963 343 S MADISON AVE APT 19      PASADENA, CA 91101

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/5/2025 Conditional Approval JOAQUIN GREENOUGH
PLUMBING-Rough 8/7/2025 Partial Approval MATTHEW NELSON
Underground Mechanical 8/7/2025 Partial Approval MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 8/11/2025 Approved DAVID ANDERSON
BUILDING-Rough-Frame 8/15/2025 Partial Approval DAVID ANDERSON
Green Building Rough 8/15/2025 Not Ready for Inspection DAVID ANDERSON
Insulation 8/15/2025 Not Ready for Inspection DAVID ANDERSON
Wood Frame 8/15/2025 Not Ready for Inspection DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 8/19/2025 Partial Approval DAVID ANDERSON
Insulation 8/19/2025 Partial Approval DAVID ANDERSON
ELECTRICAL-Rough 9/8/2025 Approved DAVID ANDERSON
PLUMBING-Rough 9/8/2025 Approved DAVID ANDERSON
BUILDING-Rough-Frame 9/12/2025 Not Ready for Inspection DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 9/12/2025 Approved DAVID ANDERSON
Green Building Rough 9/12/2025 Not Ready for Inspection DAVID ANDERSON
HVAC-Rough 9/12/2025 Not Ready for Inspection DAVID ANDERSON
HVAC-Rough 9/22/2025 Corrections Issued DAVID ANDERSON
BUILDING-Rough-Frame 9/29/2025 Approved DAVID ANDERSON
Green Building Rough 9/29/2025 Approved DAVID ANDERSON
HVAC-Rough 9/29/2025 Approved DAVID ANDERSON
Interior/Exterior Lathing 10/15/2025 Approved CHRISTOPHER MORFIN
Insulation 10/20/2025 Approved DAVID ANDERSON
Drywall Nailing 10/29/2025 Approved DAVID ANDERSON
Shower Pan 11/4/2025 Approved DAVID ANDERSON
Interior/Exterior Lathing 11/6/2025 Approved LOUIS ESCOTO
Sewer 11/20/2025 Partial Approval DAVID ANDERSON
Final 12/23/2025 Corrections Issued DAVID ANDERSON
ELECTRICAL-Final 12/30/2025 Not Ready for Inspection MATTHEW NELSON
HVAC-Final 12/30/2025 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Final 12/30/2025 Not Ready for Inspection MATTHEW NELSON
Service/Power Release 12/30/2025 Approved MATTHEW NELSON
Final 1/26/2026 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 1/26/2026 Approved MATTHEW NELSON
Green Building Final 1/26/2026 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 1/26/2026 SGSOV Approved MATTHEW NELSON
Smoke Detectors 1/26/2026 Approved MATTHEW NELSON
Final 1/29/2026 Corrections Issued DAVID ANDERSON
Green Building Final 1/29/2026 Approved DAVID ANDERSON
Final 2/3/2026 OK to Issue CofO DAVID ANDERSON