- Permit Issued
- Issued on 6/26/2025
- Issuing Office
- Current Status
- CofO Issued on 12/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/15/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2025 | NGHI SU |
| Corrections Issued | 5/21/2025 | NGHI SU |
| Applicant returned to address corrections | 6/24/2025 | AUNG SOE |
| Plan Check Approved | 6/24/2025 | AUNG SOE |
| Issued | 6/26/2025 | APPLICANT |
| CofO in Progress | 12/9/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 12/19/2025 | RUBEN SALAS |
| CofO Issued | 12/19/2025 | RUBEN SALAS |
| Permit Finaled | 12/19/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/10/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 6/10/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Fernandez,, Agapito B; Lic. No.: C56546 | 7400 E SLAUSON AVE STE S COMMERCE, CA 90040 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/18/2025 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 8/21/2025 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/21/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 9/9/2025 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 9/9/2025 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 9/9/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/1/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 10/1/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/7/2025 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 10/7/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Insulation | 10/7/2025 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 10/7/2025 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 10/15/2025 | Approved | CHRISTOPHER MORFIN |
| Interior/Exterior Lathing | 10/15/2025 | Approved | CHRISTOPHER MORFIN |
| BUILDING-Rough-Frame | 11/20/2025 | Approved | JENNIFER RABUCHIN |
| Final | 11/20/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 11/20/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 11/20/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 11/20/2025 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 11/20/2025 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 11/20/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 12/10/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 12/10/2025 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 12/10/2025 | Approved | JENNIFER RABUCHIN |