13003-13005 W KAMLOOPS ST 91331

Certificate Information: 13003-13005 W KAMLOOPS ST 91331

Application / Permit
25014-20000-02086
Plan Check / Job No.
B25VN13110
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
21'-4" X 23'-4" ADDITION OF A NEW ACCESSORY DWELLING UNIT PER LAMC12.22A.33(c) and(e) TO THE EXISTING SINGLE FAMILY DWELLING
Permit Issued
Issued on 7/30/2025
Issuing Office
Current Status
CofO Issued on 6/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/9/2025 APPLICANT
Assigned to Plan Check Engineer 5/15/2025 DANIEL ABRAMYAN
Corrections Issued 5/17/2025 DANIEL ABRAMYAN
Quality Review Completed 5/22/2025 OMID HEDAYAT
Applicant returned to address corrections 7/17/2025 DANIEL ABRAMYAN
Plan Check Approved 7/28/2025 DANIEL ABRAMYAN
Issued 7/30/2025 APPLICANT
CofO in Progress 4/17/2026 JAVIER RAMOS JR
CofO Issued 6/2/2026 RUBEN SALAS
Permit Finaled 6/2/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/23/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 5/23/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 5/28/2025 BIAINA HARITUNIAN
Sewer availability Cleared 5/28/2025 BIAINA HARITUNIAN
Clean Up Green Up Cleared 6/4/2025 ALEX VELA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/8/2025 Conditional Approval JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 8/11/2025 Approved MICHEL ABAJAN
Footing/Foundation/Slab 8/11/2025 Approved MICHEL ABAJAN
METHANE-Barrier 8/11/2025 Approved MICHEL ABAJAN
METHANE-Subgrade 8/11/2025 Approved MICHEL ABAJAN
Underground Mechanical 8/18/2025 No Access for Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 8/19/2025 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 8/19/2025 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 10/15/2025 Approved MICHEL ABAJAN
Green Building Rough 10/15/2025 Approved MICHEL ABAJAN
METHANE-Rough 10/15/2025 Approved MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 10/15/2025 Approved MICHEL ABAJAN
Insulation 11/5/2025 Approved MICHEL ABAJAN
Drywall Nailing 11/19/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 11/21/2025 Approved MICHEL ABAJAN
Shower Pan 11/21/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 3/9/2026 No Access for Inspection MICHEL ABAJAN
Final 3/9/2026 No Access for Inspection MICHEL ABAJAN
Green Building Final 3/9/2026 No Access for Inspection MICHEL ABAJAN
HVAC-Final 3/9/2026 No Access for Inspection MICHEL ABAJAN
PLUMBING-Final 3/9/2026 No Access for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 3/9/2026 SGSOV Not Ready MICHEL ABAJAN
Service/Power Release 3/9/2026 No Access for Inspection MICHEL ABAJAN
Smoke Detectors 3/9/2026 No Access for Inspection MICHEL ABAJAN
ELECTRICAL-Final 4/16/2026 Approved JAVIER RAMOS JR
Final 4/16/2026 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 4/16/2026 Approved JAVIER RAMOS JR
HVAC-Final 4/16/2026 Approved JAVIER RAMOS JR
PLUMBING-Final 4/16/2026 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 4/16/2026 SGSOV Approved JAVIER RAMOS JR
Service/Power Release 4/16/2026 Approved JAVIER RAMOS JR
Smoke Detectors 4/16/2026 Approved JAVIER RAMOS JR