7789-7791 S TOLAND AVE 90045
Certificate Information: 7789-7791 S TOLAND AVE 90045
- Application / Permit
- 25014-20000-02081
- Plan Check / Job No.
- B25VN13066
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW ADDITION TO (E) ATTACHED GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e). ENCLOSE AND CONVERT A PORTION OF (E) PORCH TO SFD.
- Permit Issued
- Issued on 7/24/2025
- Issuing Office
- Metro
- Current Status
- Issued on 7/24/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/9/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2025 | ARTIN ZARUKIAN |
| Corrections Issued | 5/17/2025 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 5/20/2025 | APPLICANT |
| Plan Check Approved | 6/5/2025 | GIOVANNY CHAVEZ |
| Issued | 7/24/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/30/2025 | RYAN CASTRO |
| Grading Pre-Inspection | Cleared | 6/2/2025 | LANNY MERRICK |
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 6/3/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 6/4/2025 | RYAN CASTRO |
Contact Information
| Contractor | Cantarero Construction; Lic. No.: 1114527-B | 2928 GRAND AVE HUNTINGTON PARK, CA 90255 |
| Engineer | Pinzon,, Eduardo Andres; Lic. No.: C74869 | 821 W SPRUCE ST WEST COVINA, CA 91790 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/14/2025 | Partial Inspection | JESUS PINEDA |
| Sewer | 8/20/2025 | Partial Approval | RUBEN RIVAS |
| Underground Mechanical | 8/20/2025 | Partial Approval | RUBEN RIVAS |
| Footing/Foundation/Slab | 8/22/2025 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2025 | Partial Approval | JESUS PINEDA |
| Footing/Foundation/Slab | 9/11/2025 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 12/3/2025 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2025 | Corrections Issued | JESUS PINEDA |
| HVAC-Rough | 12/3/2025 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 12/3/2025 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 1/27/2026 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2026 | Not Ready for Inspection | JESUS PINEDA |
| BUILDING-Rough-Frame | 2/4/2026 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2026 | Approved | JESUS PINEDA |
| Green Building Rough | 2/4/2026 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 2/4/2026 | Partial Approval | JESUS PINEDA |
| Insulation | 2/9/2026 | Approved | JESUS PINEDA |
| Drywall Nailing | 3/3/2026 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 3/6/2026 | Approved | JESUS PINEDA |
| Shower Pan | 3/6/2026 | Approved | JESUS PINEDA |
| Pre-Inspection | 4/29/2026 | Partial Inspection | JESUS PINEDA |
| ELECTRICAL-Final | 6/10/2026 | Corrections Issued | MICHAEL LEWIS |
| ELECTRICAL-Final | 6/23/2026 | Corrections Issued | MICHAEL LEWIS |
| ELECTRICAL-Final | 6/30/2026 | Approved | MICHAEL LEWIS |
| Service/Power Release | 6/30/2026 | Approved | MICHAEL LEWIS |