7789-7791 S TOLAND AVE 90045

Certificate Information: 7789-7791 S TOLAND AVE 90045

Application / Permit
25014-20000-02081
Plan Check / Job No.
B25VN13066
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW ADDITION TO (E) ATTACHED GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e). ENCLOSE AND CONVERT A PORTION OF (E) PORCH TO SFD.
Permit Issued
Issued on 7/24/2025
Issuing Office
Metro
Current Status
Issued on 7/24/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/9/2025 APPLICANT
Assigned to Plan Check Engineer 5/16/2025 ARTIN ZARUKIAN
Corrections Issued 5/17/2025 ARTIN ZARUKIAN
Building Plans Picked Up 5/20/2025 APPLICANT
Plan Check Approved 6/5/2025 GIOVANNY CHAVEZ
Issued 7/24/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/30/2025 RYAN CASTRO
Grading Pre-Inspection Cleared 6/2/2025 LANNY MERRICK
Eng Process Fee Ord 176,300 Cleared 6/3/2025 RYAN CASTRO
Sewer availability Cleared 6/3/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 6/4/2025 RYAN CASTRO

Contact Information

Contractor Cantarero Construction; Lic. No.: 1114527-B 2928 GRAND AVE      HUNTINGTON PARK, CA 90255
Engineer Pinzon,, Eduardo Andres; Lic. No.: C74869 821 W SPRUCE ST      WEST COVINA, CA 91790

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/14/2025 Partial Inspection JESUS PINEDA
Sewer 8/20/2025 Partial Approval RUBEN RIVAS
Underground Mechanical 8/20/2025 Partial Approval RUBEN RIVAS
Footing/Foundation/Slab 8/22/2025 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 9/11/2025 Partial Approval JESUS PINEDA
Footing/Foundation/Slab 9/11/2025 Approved JESUS PINEDA
ELECTRICAL-Rough 12/3/2025 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 12/3/2025 Corrections Issued JESUS PINEDA
HVAC-Rough 12/3/2025 Approved JESUS PINEDA
PLUMBING-Rough 12/3/2025 Approved JESUS PINEDA
ELECTRICAL-Rough 1/27/2026 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 1/27/2026 Not Ready for Inspection JESUS PINEDA
BUILDING-Rough-Frame 2/4/2026 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 2/4/2026 Approved JESUS PINEDA
Green Building Rough 2/4/2026 Approved JESUS PINEDA
Interior/Exterior Lathing 2/4/2026 Partial Approval JESUS PINEDA
Insulation 2/9/2026 Approved JESUS PINEDA
Drywall Nailing 3/3/2026 Approved JESUS PINEDA
Interior/Exterior Lathing 3/6/2026 Approved JESUS PINEDA
Shower Pan 3/6/2026 Approved JESUS PINEDA
Pre-Inspection 4/29/2026 Partial Inspection JESUS PINEDA
ELECTRICAL-Final 6/10/2026 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Final 6/23/2026 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Final 6/30/2026 Approved MICHAEL LEWIS
Service/Power Release 6/30/2026 Approved MICHAEL LEWIS