6527 N BEEMAN AVE 91606

Certificate Information: 6527 N BEEMAN AVE 91606

Application / Permit
25014-20000-02055
Plan Check / Job No.
B25VN12929
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO AND CONVERT THE (E) GARAGE TO AN ACCESSORY DWELLING UNIT PER GC 66323(a)(2)
Permit Issued
Issued on 5/29/2025
Issuing Office
Current Status
CofO Issued on 12/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/8/2025 APPLICANT
Assigned to Plan Check Engineer 5/16/2025 KAMYAR EMAMI
Corrections Issued 5/16/2025 KAMYAR EMAMI
Building Plans Picked Up 5/19/2025 APPLICANT
Plan Check Approved 5/27/2025 JESSE ARELLANO
Issued 5/29/2025 APPLICANT
Permit Finaled 12/17/2025 RUBEN SALAS
CofO Issued 12/17/2025 RUBEN SALAS
Permit Finaled 12/17/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/22/2025 BIAINA HARITUNIAN
Construction near power lines Cleared 5/23/2025 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 5/23/2025 BIAINA HARITUNIAN
Sewer availability Cleared 5/23/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 5/27/2025 LEE GUILBEAUX
Hold Cleared 6/13/2025 ALEXIS SCHULTZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/16/2025 Conditional Approval JOAQUIN GREENOUGH
PLUMBING-Rough 6/17/2025 Partial Approval GAREN HAYRAPETYAN
Footing/Foundation/Slab 6/23/2025 Approved JOAQUIN GREENOUGH
Gas Test 7/18/2025 Partial Approval OGANES TARAKHCHYAN
Insulation 7/18/2025 Partial Approval OGANES TARAKHCHYAN
Underground Mechanical 7/18/2025 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 8/4/2025 Not Ready for Inspection GAREN HAYRAPETYAN
ELECTRICAL-Rough 8/4/2025 Approved GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 8/4/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 8/4/2025 Not Ready for Inspection GAREN HAYRAPETYAN
HVAC-Rough 8/4/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 8/4/2025 Approved GAREN HAYRAPETYAN
Sewer 8/4/2025 Partial Approval GAREN HAYRAPETYAN
BUILDING-Rough-Frame 8/11/2025 Approved OGANES TARAKHCHYAN
Green Building Rough 8/11/2025 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 8/11/2025 Partial Approval OGANES TARAKHCHYAN
Shower Pan 8/11/2025 Approved OGANES TARAKHCHYAN
Insulation 8/13/2025 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 8/19/2025 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 9/3/2025 Approved OGANES TARAKHCHYAN
Final 10/14/2025 Corrections Issued OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 10/14/2025 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 10/14/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Final 10/24/2025 Corrections Issued OGANES TARAKHCHYAN
Smoke Detectors 10/24/2025 Approved OGANES TARAKHCHYAN
Final 11/21/2025 Not Ready for Inspection WAYNE REGESTER
Green Building Final 11/21/2025 Approved WAYNE REGESTER
Service/Power Release 11/21/2025 Approved WAYNE REGESTER
Final 12/15/2025 Partial Approval WAYNE REGESTER