16345-16347 W RAYEN ST 91343
Certificate Information: 16345-16347 W RAYEN ST 91343
- Application / Permit
- 25014-20000-02022
- Plan Check / Job No.
- B25VN12758
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO AND CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (e).
- Permit Issued
- Issued on 7/15/2025
- Issuing Office
- Current Status
- CofO Issued on 6/10/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/14/2025 | ARTIN ZARUKIAN |
| Corrections Issued | 5/14/2025 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 5/16/2025 | APPLICANT |
| Plan Check Approved | 7/15/2025 | GIOVANNY CHAVEZ |
| Issued | 7/15/2025 | APPLICANT |
| CofO in Progress | 4/29/2026 | KIRK SANDERS |
| CofO Issued | 6/10/2026 | RUBEN SALAS |
| Permit Finaled | 6/10/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/27/2025 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 5/27/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 5/28/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 5/28/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 5/28/2025 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 7/2/2025 | FIPE LEILUA |
| Miscellaneous | Cleared | 7/2/2025 | FIPE LEILUA |
| Construction near power lines | Cleared | 7/14/2025 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/29/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 10/6/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 10/10/2025 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 10/30/2025 | Not Ready for Inspection | RYAN SALAZAR |
| BUILDING-Rough-Frame | 11/13/2025 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 11/13/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 11/13/2025 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 11/13/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 11/13/2025 | Partial Approval | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 11/13/2025 | Approved | GAREN HAYRAPETYAN |
| Insulation | 11/21/2025 | Approved | WAYNE REGESTER |
| Drywall Nailing | 11/26/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 11/26/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Shower Pan | 11/26/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 12/4/2025 | Not Ready for Inspection | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 12/9/2025 | Approved | MICHAEL CORTEZ |
| Final | 4/10/2026 | Not Ready for Inspection | WAYNE REGESTER |
| Green Building Final | 4/10/2026 | Corrections Issued | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 4/10/2026 | SGSOV Approved | WAYNE REGESTER |
| Smoke Detectors | 4/10/2026 | Approved | WAYNE REGESTER |
| Underground Mechanical | 4/10/2026 | Approved | WAYNE REGESTER |
| Final | 4/21/2026 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 4/21/2026 | Not Ready for Inspection | KIRK SANDERS |
| Final | 4/27/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Final | 4/27/2026 | Approved | GAREN HAYRAPETYAN |
| Final | 4/29/2026 | OK to Issue CofO | KIRK SANDERS |