3791 S EDGEHILL DR 90018
Certificate Information: 3791 S EDGEHILL DR 90018
- Application / Permit
- 25014-20000-02013
- Plan Check / Job No.
- B25VN12733
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- 4' X 20'ADDITION TO EXPAND THE (E) DETACHED GARAGE, ALL WORK PER WFPP.
- Permit Issued
- Issued on 5/12/2025
- Issuing Office
- Current Status
- CofO Issued on 11/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/6/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2025 | ISIS ARGUETA |
| Corrections Issued | 5/6/2025 | ISIS ARGUETA |
| Issued | 5/12/2025 | APPLICANT |
| CofO in Progress | 11/13/2025 | LUIS CASTRO |
| Permit Finaled | 11/14/2025 | DEROLD HAUFF |
| CofO Issued | 11/14/2025 | DEROLD HAUFF |
| Permit Finaled | 11/14/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/7/2025 | BRYAN GODINEZ |
| Construction near power lines | Cleared | 5/9/2025 | EDGAR PASCUA |
| Eng Process Fee Ord 176,300 | Cleared | 5/9/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Bela Development; Lic. No.: 1038287-B | 1023 1/2 ABBOT KINNEY BLVD VENICE, CA 90291 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/15/2025 | Approved | LUIS CASTRO |
| Excavation/Setback/Form/Re-Bar | 5/15/2025 | Approved | LUIS CASTRO |
| Footing/Foundation/Slab | 5/15/2025 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2025 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2025 | Corrections Issued | LUIS CASTRO |
| ELECTRICAL-Rough | 6/16/2025 | Approved | LUIS CASTRO |
| HVAC-Rough | 6/16/2025 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 6/16/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 10/23/2025 | Approved | LUIS CASTRO |
| Final | 10/23/2025 | Corrections Issued | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2025 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 10/23/2025 | SGSOV Approved | LUIS CASTRO |
| Smoke Detectors | 10/23/2025 | Approved | LUIS CASTRO |
| Special/Order Compliance | 10/23/2025 | Approved | LUIS CASTRO |
| Final | 11/13/2025 | OK to Issue CofO | LUIS CASTRO |