7040 N TYRONE AVE 91405

Certificate Information: 7040 N TYRONE AVE 91405

Application / Permit
25014-20000-01968
Plan Check / Job No.
B25VN12461
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan MAJOR REMODEL AND ADDITION IN THE FRONT AND BACK OF (E) SFD. WORK DONE PER ENGINEER ***13D SPRINKLER REQUIRED***
Permit Issued
Issued on 6/18/2025
Issuing Office
Current Status
CofO Issued on 4/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/5/2025 APPLICANT
Assigned to Plan Check Engineer 5/8/2025 KHUONG TRUONG
Corrections Issued 5/16/2025 KHUONG TRUONG
Quality Review Completed 6/5/2025 JOSE RODRIGUEZ
Plan Check Approved 6/16/2025 KHUONG TRUONG
Issued 6/18/2025 APPLICANT
CofO in Progress 2/25/2026 VINCENT HANLEY
CofO Issued 4/2/2026 RUBEN SALAS
Permit Finaled 4/2/2026 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/11/2025 MICHAEL BROWN
Roof/Waste drainage to street Cleared 6/11/2025 MICHAEL BROWN
Sewer availability Cleared 6/11/2025 MICHAEL BROWN

Contact Information

Contractor Owner-Builder       ,
Engineer Vartanian,, Albert; Lic. No.: NA39989       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/22/2025 Approved JENNIFER RABUCHIN
Deputy Drilled-In Anchors 9/4/2025 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 9/4/2025 Partial Approval RYAN SALAZAR
Green Building Rough 9/4/2025 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Rough 9/4/2025 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 9/9/2025 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 10/7/2025 Approved RYAN SALAZAR
BUILDING-Rough-Frame 10/29/2025 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 10/29/2025 Approved RYAN SALAZAR
Green Building Rough 10/29/2025 Approved RYAN SALAZAR
HVAC-Rough 10/29/2025 Approved RYAN SALAZAR
PLUMBING-Rough 10/29/2025 Approved RYAN SALAZAR
Insulation 11/3/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 11/3/2025 Partial Approval RYAN SALAZAR
Drywall Nailing 11/7/2025 Approved JACK KARGODORIAN
Shower Pan 12/5/2025 Approved DAVID MATSON
Underground Mechanical 12/5/2025 Partial Approval DAVID MATSON
ELECTRICAL-Final 1/21/2026 Conditional Approval RYAN SALAZAR
BUILDING-Rough-Frame 2/18/2026 Approved KIRK SANDERS
Final 2/18/2026 Corrections Issued KIRK SANDERS
Green Building Final 2/18/2026 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 2/18/2026 SGSOV Approved KIRK SANDERS
Smoke Detectors 2/18/2026 Corrections Issued KIRK SANDERS
ELECTRICAL-Final 2/23/2026 Approved VINCENT HANLEY
Final 2/23/2026 OK to Issue CofO VINCENT HANLEY
HVAC-Final 2/23/2026 Approved VINCENT HANLEY
PLUMBING-Final 2/23/2026 Approved VINCENT HANLEY
Smoke Detectors 2/23/2026 Approved VINCENT HANLEY