2227 N NELLA VISTA AVE 90027

Certificate Information: 2227 N NELLA VISTA AVE 90027

Application / Permit
25014-20000-01934
Plan Check / Job No.
B25VN12241
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMOVE 7'-5" X 20'-2" AND ADD (N) 15' X 20'-2" TO (E) GARAGE AND CONVERT ENTIRE STRUCTURE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1)3 ALL WORK PER ENGINEERING
Permit Issued
Issued on 6/12/2025
Issuing Office
Metro
Current Status
CofO Issued on 11/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/1/2025 APPLICANT
Assigned to Plan Check Engineer 5/7/2025 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 5/12/2025 SEWADA ZADOORIAN MILAGARDI
Building Plans Picked Up 5/13/2025 APPLICANT
Plan Check Approved 6/10/2025 SEWADA ZADOORAN MILAGARDI
Issued 6/12/2025 APPLICANT
CofO in Progress 11/14/2025 ENRIQUE MIRELES
Permit Finaled 11/16/2025 DEROLD HAUFF
CofO Issued 11/16/2025 DEROLD HAUFF
Permit Finaled 11/16/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/21/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 5/22/2025 MICHAEL BROWN
Sewer availability Cleared 5/22/2025 MICHAEL BROWN
Hydrant and Access approval Cleared 6/3/2025 FRANK GOMEZ
Roof/Waste drainage to street Cleared 6/6/2025 MICHAEL BROWN
Grading Pre-Inspection Cleared 6/10/2025 SEWADA ZADOORAN MILAGARDI

Contact Information

Architect Miller,, Michael; Lic. No.: C26956 12756 MITCHELL AVE      LOS ANGELES, CA 90066
Contractor Owner-Builder       ,

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/24/2025 Partial Approval ALIZAH MAYAGOITIA
Underground Mechanical 7/14/2025 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 7/15/2025 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 7/15/2025 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 8/8/2025 Not Ready for Inspection BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 8/8/2025 Approved BRENDAN MORELLI
Green Building Rough 8/8/2025 Not Ready for Inspection BRENDAN MORELLI
PLUMBING-Rough 8/8/2025 Partial Approval BRENDAN MORELLI
Underground Mechanical 8/8/2025 Partial Approval BRENDAN MORELLI
ELECTRICAL-Rough 8/15/2025 Approved ENRIQUE MIRELES
HVAC-Rough 8/15/2025 Approved ENRIQUE MIRELES
PLUMBING-Rough 8/15/2025 Approved ENRIQUE MIRELES
Insulation 8/20/2025 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 8/20/2025 Not Ready for Inspection ENRIQUE MIRELES
Shower Pan 8/20/2025 Approved ENRIQUE MIRELES
Drywall Nailing 8/26/2025 Not Ready for Inspection ALEX COLIN
Green Building Rough 8/26/2025 Not Ready for Inspection ALEX COLIN
Interior/Exterior Lathing 8/26/2025 Not Ready for Inspection ALEX COLIN
BUILDING-Rough-Frame 8/27/2025 Approved ANTHONY RAMOS
Drywall Nailing 8/27/2025 Approved ANTHONY RAMOS
Green Building Rough 8/27/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 8/27/2025 Approved ANTHONY RAMOS
Final 10/31/2025 OK to Issue CofO ENRIQUE MIRELES
Green Building Final 10/31/2025 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 10/31/2025 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 10/31/2025 Approved ENRIQUE MIRELES