18754 W COHASSET ST 91335
Certificate Information: 18754 W COHASSET ST 91335
- Application / Permit
- 25014-20000-01924
- Plan Check / Job No.
- B25VN12132
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION BATHROOMS TO SFD & INTERIOR REMODEL. ** see comments **
- Permit Issued
- Issued on 6/6/2025
- Issuing Office
- Current Status
- CofO Issued on 6/24/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/7/2025 | KAVIAN REFAHI |
| Corrections Issued | 5/8/2025 | KAVIAN REFAHI |
| Plan Check Approved | 6/4/2025 | KAVIAN REFAHI |
| Issued | 6/6/2025 | APPLICANT |
| CofO in Progress | 5/21/2026 | ARUTYUN MADATYAN |
| Permit Finaled | 6/24/2026 | JOHN JANSON |
| CofO Issued | 6/24/2026 | JOHN JANSON |
| Permit Finaled | 6/24/2026 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/14/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 5/15/2025 | MICHAEL BROWN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kazemi,, Milad; Lic. No.: C92143 | 28025 DOROTHY DR STE 202 AGOURA HILLS, CA 91301 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/25/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 7/25/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 8/1/2025 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 8/15/2025 | Corrections Issued | ARUTYUN MADATYAN |
| PLUMBING-Rough | 8/15/2025 | Partial Approval | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 8/25/2025 | Partial Approval | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 9/15/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 9/15/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 9/15/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 9/25/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 9/25/2025 | Approved | ARUTYUN MADATYAN |
| Insulation | 9/25/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 9/25/2025 | Approved | ARUTYUN MADATYAN |
| Rough-Elec/Plmb/HVAC | 9/25/2025 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 10/3/2025 | Approved | ARUTYUN MADATYAN |
| Final | 11/3/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 11/3/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 11/3/2025 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Smoke Detectors | 11/3/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Final | 12/1/2025 | Conditional Approval | ARUTYUN MADATYAN |
| Green Building Final | 12/1/2025 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 12/1/2025 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Smoke Detectors | 12/1/2025 | Approved | ARUTYUN MADATYAN |
| Final | 2/13/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 2/13/2026 | SGSOV Approved | ARUTYUN MADATYAN |
| Final | 3/25/2026 | Not Ready for Inspection | JUAN ALVARADO |
| Final | 4/13/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 5/20/2026 | Approved | ARUTYUN MADATYAN |
| Final | 5/20/2026 | OK to Issue CofO | ARUTYUN MADATYAN |
| HVAC-Final | 5/20/2026 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 5/20/2026 | Approved | ARUTYUN MADATYAN |
| Service/Power Release | 5/20/2026 | Approved | ARUTYUN MADATYAN |