17401 W BLYTHE ST 91325

Certificate Information: 17401 W BLYTHE ST 91325

Application / Permit
25014-20000-01919
Plan Check / Job No.
B25VN12110
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REAR ADDITION TO THE (E) SINGLE FAMILY DWELLING
Permit Issued
Issued on 8/18/2025
Issuing Office
Current Status
CofO Issued on 4/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/14/2025 APPLICANT
Assigned to Plan Check Engineer 5/19/2025 SERGIO MUNIZ
Corrections Issued 5/20/2025 SERGIO MUNIZ
Applicant returned to address corrections 6/21/2025 GIOVANNY CHAVEZ
Applicant returned to address corrections 7/1/2025 SERGIO MUNIZ
Plan Check Approved 7/11/2025 GURUNATH NESARAJAH
Issued 8/18/2025 APPLICANT
CofO in Progress 3/23/2026 KIRK SANDERS
Permit Finaled 4/2/2026 RUBEN SALAS
CofO Issued 4/2/2026 RUBEN SALAS
Permit Finaled 4/2/2026 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/4/2025 BRYAN GODINEZ
Sewer availability Cleared 6/4/2025 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 6/6/2025 BRYAN GODINEZ

Contact Information

Contractor D K R Construction Inc; Lic. No.: 1070450-B       ,
Engineer Kaballo,, Amir; Lic. No.: NA90707       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/12/2025 Partial Approval WAYNE REGESTER
Deputy Drilled-In Anchors 11/13/2025 Conditional Approval JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 11/18/2025 Approved WAYNE REGESTER
Floor/Roof Diaphrgm/Shear Wall 11/25/2025 Partial Approval GAREN HAYRAPETYAN
BUILDING-Rough-Frame 12/4/2025 Partial Approval GAREN HAYRAPETYAN
ELECTRICAL-Rough 12/4/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 12/4/2025 Not Ready for Inspection GAREN HAYRAPETYAN
HVAC-Rough 12/4/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 12/4/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 12/19/2025 Approved CHRISTOPHER MORFIN
Insulation 12/24/2025 Corrections Issued MICHAEL CORTEZ
Drywall Nailing 1/2/2026 Approved GAREN HAYRAPETYAN
Insulation 1/2/2026 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 1/2/2026 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 3/9/2026 Approved KIRK SANDERS
ELECTRICAL-Final 3/9/2026 Approved KIRK SANDERS
Final 3/9/2026 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 3/9/2026 Approved KIRK SANDERS
Green Building Final 3/9/2026 Not Ready for Inspection KIRK SANDERS
Green Building Rough 3/9/2026 Approved KIRK SANDERS
HVAC-Final 3/9/2026 Partial Approval KIRK SANDERS
PLUMBING-Final 3/9/2026 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 3/9/2026 SGSOV Not Ready KIRK SANDERS
Service/Power Release 3/9/2026 Approved KIRK SANDERS
Smoke Detectors 3/9/2026 Approved KIRK SANDERS
Final 3/18/2026 OK to Issue CofO KIRK SANDERS
Green Building Final 3/18/2026 Approved KIRK SANDERS
HVAC-Final 3/18/2026 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 3/18/2026 SGSOV Approved KIRK SANDERS