9340-9342 N CREBS AVE 91324

Certificate Information: 9340-9342 N CREBS AVE 91324

Application / Permit
25014-20000-01891
Plan Check / Job No.
B25VN11922
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO AN ACCESSORY DWELLING UNIT PER GC 66323(a)(1) AND ADD NEW ATTACHED STORAGE TO (E) SFD
Permit Issued
Issued on 8/14/2025
Issuing Office
Current Status
CofO Issued on 11/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2025 APPLICANT
Assigned to Plan Check Engineer 5/2/2025 KAMYAR EMAMI
Corrections Issued 5/5/2025 KAMYAR EMAMI
Applicant returned to address corrections 7/28/2025 KAMYAR EMAMI
Applicant returned to address corrections 8/6/2025 KAMYAR EMAMI
Plan Check Approved 8/13/2025 KAMYAR EMAMI
Issued 8/14/2025 APPLICANT
CofO in Progress 11/19/2025 KRISTEN CAUSEY
CofO in Progress 11/19/2025 KRISTEN CAUSEY
CofO in Progress 11/20/2025 KRISTEN CAUSEY
Permit Finaled 11/29/2025 MICHAEL PELHAM
CofO Issued 11/29/2025 MICHAEL PELHAM
Permit Finaled 11/29/2025 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 7/7/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 7/7/2025 MICHAEL BROWN
Sewer availability Cleared 7/7/2025 MICHAEL BROWN
Roof/Waste drainage to street Cleared 7/24/2025 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/19/2025 Conditional Approval KRISTEN CAUSEY
PLUMBING-Rough 8/19/2025 Partial Approval KRISTEN CAUSEY
Deputy Drilled-In Anchors 8/21/2025 Conditional Approval HENRY KIM
BUILDING-Rough-Frame 9/3/2025 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 9/3/2025 Not Ready for Inspection DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 9/3/2025 Approved DAVID SCANTLIN
PLUMBING-Rough 9/3/2025 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 9/12/2025 Approved KRISTEN CAUSEY
ELECTRICAL-Rough 9/12/2025 Approved KRISTEN CAUSEY
Green Building Rough 9/12/2025 Approved KRISTEN CAUSEY
PLUMBING-Rough 9/12/2025 Approved KRISTEN CAUSEY
Insulation 9/16/2025 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 9/16/2025 Partial Approval KRISTEN CAUSEY
Drywall Nailing 9/22/2025 Approved DAVID SCANTLIN
Interior/Exterior Lathing 9/22/2025 Approved DAVID SCANTLIN
Final 10/15/2025 Corrections Issued DAVID SCANTLIN
Footing/Foundation/Slab 10/15/2025 Approved DAVID SCANTLIN
Green Building Final 10/15/2025 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 10/15/2025 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 10/15/2025 Not Ready for Inspection DAVID SCANTLIN
Final 10/21/2025 Corrections Issued KRISTEN CAUSEY
Green Building Final 10/21/2025 Approved KRISTEN CAUSEY
Smoke Detectors 10/21/2025 Approved KRISTEN CAUSEY
Final 11/14/2025 Corrections Issued KRISTEN CAUSEY
Final 11/20/2025 OK to Issue CofO KRISTEN CAUSEY