24220 W MARIANO ST 91367
Certificate Information: 24220 W MARIANO ST 91367
- Application / Permit
- 25014-20000-01887
- Plan Check / Job No.
- B25VN11907
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) ADDITION AND REMODEL TO (E) SFD
- Permit Issued
- Issued on 5/28/2025
- Issuing Office
- Current Status
- Issued on 5/28/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/29/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2025 | JEROME MAGAT PALMA |
| Corrections Issued | 5/7/2025 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 5/9/2025 | APPLICANT |
| Plan Check Approved | 5/28/2025 | ISIS ARGUETA |
| Issued | 5/28/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/13/2025 | BRYAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/19/2025 | BRYAN GODINEZ |
| Grading Pre-Inspection | Cleared | 5/19/2025 | GERMAN RODRIGUEZ MENDOZA |
| GPI Written Notices | Cleared | 5/28/2025 | JEROME MAGAT PALMA |
Contact Information
| Contractor | Yaron Do It Inc; Lic. No.: 1081021-B | 26115 KENROSE CIRCLE CALABASAS, CA 91302 |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/23/2025 | Conditional Approval | ROBERT GOLD |
| Sewer | 7/7/2025 | Partial Approval | GEVORK IPCHYAN |
| Footing/Foundation/Slab | 7/11/2025 | Approved | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2025 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 9/10/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Green Building Rough | 9/10/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Deputy Wood Construction | 9/17/2025 | Conditional Approval | TROY SANDERS |
| ELECTRICAL-Rough | 9/17/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| PLUMBING-Rough | 9/17/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Underground Mechanical | 9/17/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Shower Pan | 9/25/2025 | Approved | TROY SANDERS |
| Insulation | 10/3/2025 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 10/3/2025 | Approved | TROY SANDERS |
| Drywall Nailing | 10/15/2025 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 1/8/2026 | Approved | GEVORK IPCHYAN |
| ELECTRICAL-Final | 1/8/2026 | Not Ready for Inspection | GEVORK IPCHYAN |
| Final | 1/8/2026 | Not Ready for Inspection | GEVORK IPCHYAN |
| Green Building Final | 1/8/2026 | Not Ready for Inspection | GEVORK IPCHYAN |
| Green Building Rough | 1/8/2026 | Approved | GEVORK IPCHYAN |
| PLUMBING-Final | 1/8/2026 | Approved | GEVORK IPCHYAN |
| SGSOV-Seismic Gas S/O Valve | 1/8/2026 | SGSOV Approved | GEVORK IPCHYAN |
| Smoke Detectors | 1/8/2026 | Approved | GEVORK IPCHYAN |