10843 N BLUCHER AVE 91344
Certificate Information: 10843 N BLUCHER AVE 91344
- Application / Permit
- 25014-20000-01885
- Plan Check / Job No.
- B25VN11873
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: 19'-9" X 18'-11"addition to existing detached garage and convered to ADU per WFPP (New Construction or Conversion of Existing per Ordinance, LAMC12.22A.33(b)(1))
- Permit Issued
- Issued on 8/28/2025
- Issuing Office
- Current Status
- Issued on 8/28/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/29/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/2/2025 | AUNG SOE |
| Corrections Issued | 5/6/2025 | AUNG SOE |
| Applicant returned to address corrections | 8/13/2025 | AUNG SOE |
| Plan Check Approved | 8/13/2025 | AUNG SOE |
| Issued | 8/28/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/11/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 5/13/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 5/13/2025 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 6/11/2025 | GEVORK KARAPETYAN |
| Construction within easement | Cleared | 6/11/2025 | GEVORK KARAPETYAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 11/18/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Underground Mechanical | 11/18/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Underground Mechanical | 12/2/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Excavation/Setback/Form/Re-Bar | 12/9/2025 | Approved | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 12/9/2025 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 12/9/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2025 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 12/30/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 12/30/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Rough | 12/30/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 12/30/2025 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 1/23/2026 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 1/23/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Wood Frame | 1/23/2026 | Partial Inspection | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2026 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 2/3/2026 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 2/3/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Drywall Nailing | 2/20/2026 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 2/20/2026 | Approved | KEVIN BERBERYAN |
| Shower Pan | 2/20/2026 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 6/5/2026 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 6/5/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 6/5/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 6/5/2026 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 6/5/2026 | Approved | CHRISTOPHER ROJAS |
| HVAC-Final | 6/5/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| MERV13>=Final | 6/5/2026 | Approved | CHRISTOPHER ROJAS |
| MERV13>=Rough | 6/5/2026 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Final | 6/5/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 6/5/2026 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Smoke Detectors | 6/5/2026 | Approved | CHRISTOPHER ROJAS |