20953 W SATICOY ST 91306
Certificate Information: 20953 W SATICOY ST 91306
- Application / Permit
- 25014-20000-01874
- Plan Check / Job No.
- B25VN11775
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING GARAGE/PATIO COVER WITH ADDITIONS INTO A 2-STORY (36'-6" X 20' IRR SHAPE) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1)
- Permit Issued
- Issued on 6/6/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/29/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/15/2025 | VAHAN JIVALAGIAN |
| Corrections Issued | 5/22/2025 | VAHAN JIVALAGIAN |
| Quality Review Completed | 5/23/2025 | OMID HEDAYAT |
| Building Plans Picked Up | 5/27/2025 | APPLICANT |
| Plan Check Approved | 6/4/2025 | VAHAN JIVALAGIAN |
| Issued | 6/6/2025 | APPLICANT |
| CofO in Progress | 2/17/2026 | ALEXANDER HANDY |
| Permit Finaled | 2/28/2026 | MICHAEL PELHAM |
| CofO Issued | 2/28/2026 | MICHAEL PELHAM |
| Permit Finaled | 2/28/2026 | MICHAEL PELHAM |
Permit Application Clearance Information
| Address approval | Cleared | 5/22/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 5/22/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 5/22/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 5/22/2025 | SAFA JAVANMARDI |
| Construction near power lines | Cleared | 5/23/2025 | TINA MIRANDA |
Contact Information
| Contractor | Eden Development & Consulting Inc; Lic. No.: 984612-B | 13455 VENTURA BLVD STE 215 SHERMAN OAKS, CA 91423 |
| Engineer | Telian,, Vartan; Lic. No.: C94330 | 11776 PIERCE ST SYLMAR, CA 91342 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/30/2025 | Conditional Approval | HENRY KIM |
| Footing/Foundation/Slab | 7/1/2025 | Corrections Issued | SCOTT SOBEL |
| PLUMBING-Rough | 7/1/2025 | Partial Approval | SCOTT SOBEL |
| Underground Mechanical | 7/1/2025 | Not Ready for Inspection | SCOTT SOBEL |
| Deputy Drilled-In Anchors | 7/7/2025 | Conditional Approval | ALEXANDER HANDY |
| Footing/Foundation/Slab | 7/17/2025 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2025 | Partial Approval | KRISTEN CAUSEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2025 | Partial Approval | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 8/20/2025 | No Access for Inspection | ALEXANDER HANDY |
| ELECTRICAL-Rough | 8/20/2025 | No Access for Inspection | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2025 | No Access for Inspection | ALEXANDER HANDY |
| Green Building Rough | 8/20/2025 | No Access for Inspection | ALEXANDER HANDY |
| PLUMBING-Rough | 8/20/2025 | No Access for Inspection | ALEXANDER HANDY |
| Rough-Elec/Plmb/HVAC | 8/20/2025 | No Access for Inspection | ALEXANDER HANDY |
| Sewer | 8/20/2025 | No Access for Inspection | ALEXANDER HANDY |
| Underground Mechanical | 8/20/2025 | No Access for Inspection | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 9/11/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| ELECTRICAL-Rough | 9/11/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Rough | 9/11/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| PLUMBING-Rough | 9/11/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Sewer | 9/11/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Shower Pan | 9/11/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Underground Mechanical | 9/11/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 9/24/2025 | Partial Approval | ALEXANDER HANDY |
| ELECTRICAL-Rough | 9/24/2025 | Approved | ALEXANDER HANDY |
| Green Building Rough | 9/24/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| HVAC-Rough | 9/24/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| PLUMBING-Rough | 9/24/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 9/29/2025 | Conditional Approval | ALEXANDER HANDY |
| Green Building Rough | 9/29/2025 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 9/29/2025 | Partial Approval | ALEXANDER HANDY |
| PLUMBING-Rough | 9/29/2025 | Corrections Issued | ALEXANDER HANDY |
| Insulation | 10/1/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 10/1/2025 | Approved | ALEXANDER HANDY |
| Shower Pan | 10/1/2025 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 10/10/2025 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 10/10/2025 | Partial Approval | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 12/2/2025 | Not Ready for Inspection | KRISTEN CAUSEY |
| Final | 12/2/2025 | Not Ready for Inspection | KRISTEN CAUSEY |
| Green Building Final | 12/2/2025 | Not Ready for Inspection | KRISTEN CAUSEY |
| SGSOV-Seismic Gas S/O Valve | 12/2/2025 | SGSOV Not Ready | KRISTEN CAUSEY |
| Smoke Detectors | 12/2/2025 | Not Ready for Inspection | KRISTEN CAUSEY |
| Pre-Inspection | 12/4/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 12/8/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Final | 12/8/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Final | 12/8/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 12/8/2025 | SGSOV Not Ready | ALEXANDER HANDY |
| Smoke Detectors | 12/8/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 1/20/2026 | Corrections Issued | ROBERT GOLD |
| Final | 1/20/2026 | Corrections Issued | ROBERT GOLD |
| Green Building Final | 1/20/2026 | Approved | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 1/20/2026 | SGSOV No Gas | ROBERT GOLD |
| Smoke Detectors | 1/20/2026 | Approved | ROBERT GOLD |
| Final | 1/23/2026 | Not Ready for Inspection | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 2/9/2026 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 2/9/2026 | Approved | ALEXANDER HANDY |
| Final | 2/9/2026 | OK to Issue CofO | ALEXANDER HANDY |
| HVAC-Final | 2/9/2026 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 2/9/2026 | Approved | ALEXANDER HANDY |