7829 N WILKINSON AVE 91605

Certificate Information: 7829 N WILKINSON AVE 91605

Application / Permit
25014-20000-01867
Plan Check / Job No.
B25VN11731
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO GARAGE AND COVERSION TO MAKE A 29'8"X20'1" 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1)3 (NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT) [2 OF 2]
Permit Issued
Issued on 1/21/2026
Issuing Office
Valley
Current Status
Issued on 1/21/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/28/2025 APPLICANT
Assigned to Plan Check Engineer 5/15/2025 MARVEL DELACRUZ
Corrections Issued 5/22/2025 MARVEL DELACRUZ
Quality Review Completed 5/29/2025 JASON HEALEY
Building Plans Picked Up 5/30/2025 APPLICANT
Applicant returned to address corrections 7/1/2025 MARVEL DELACRUZ
Applicant returned to address corrections 9/3/2025 MARVEL DELACRUZ
Plan Check Approved 9/16/2025 MARVEL DELACRUZ
Issued 1/21/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/28/2025 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/2/2025 CARLOS AGUILERA
Sewer availability Cleared 6/2/2025 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 6/27/2025 DERRICK MAGEE

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/5/2026 Partial Approval MATTHEW NELSON
PLUMBING-Rough 3/5/2026 Partial Approval MATTHEW NELSON
Pre-Inspection 3/5/2026 Partial Inspection MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 3/9/2026 Approved MATTHEW NELSON
PLUMBING-Rough 4/7/2026 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 4/17/2026 Not Ready for Inspection NICHOLAS TROWBRIDGE
HVAC-Rough 4/17/2026 Not Ready for Inspection NICHOLAS TROWBRIDGE
PLUMBING-Rough 4/17/2026 Not Ready for Inspection NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 4/24/2026 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Rough 4/24/2026 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 4/24/2026 Not Ready for Inspection MATTHEW NELSON
Green Building Rough 4/24/2026 Approved MATTHEW NELSON
HVAC-Rough 4/24/2026 Approved MATTHEW NELSON
MERV13>=Rough 4/24/2026 Approved MATTHEW NELSON
PLUMBING-Rough 4/24/2026 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 5/4/2026 Approved MATTHEW NELSON