19834-19836 W HAMLIN ST 91367

Certificate Information: 19834-19836 W HAMLIN ST 91367

Application / Permit
25014-20000-01802
Plan Check / Job No.
B25VN11339
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO AND CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (e).
Permit Issued
Issued on 5/30/2025
Issuing Office
Current Status
CofO Issued on 1/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/23/2025 APPLICANT
Assigned to Plan Check Engineer 4/28/2025 OMAR GARNICA
Corrections Issued 4/29/2025 OMAR GARNICA
Applicant returned to address corrections 5/27/2025 GIOVANNY CHAVEZ
Plan Check Approved 5/28/2025 GIOVANNY CHAVEZ
Issued 5/30/2025 APPLICANT
CofO in Progress 1/12/2026 HENRY KIM
Permit Finaled 1/16/2026 JOHN JANSON
CofO Issued 1/16/2026 JOHN JANSON
Permit Finaled 1/16/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/12/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 5/12/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 5/14/2025 SAFA JAVANMARDI
Sewer availability Cleared 5/14/2025 SAFA JAVANMARDI

Contact Information

Contractor Owner-Builder       ,
Engineer Maalouf,, Sami; Lic. No.: NA53210       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/25/2025 Partial Approval SCOTT SOBEL
Sewer 8/25/2025 Approved SCOTT SOBEL
Special/Order Compliance 8/25/2025 Partial Inspection HENRY KIM
Deputy Drilled-In Anchors 8/29/2025 Approved ALEXANDER HANDY
Footing/Foundation/Slab 8/29/2025 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 10/28/2025 Corrections Issued ALEXANDER HANDY
ELECTRICAL-Rough 10/28/2025 Approved ALEXANDER HANDY
Green Building Rough 10/28/2025 Not Ready for Inspection ALEXANDER HANDY
PLUMBING-Rough 10/28/2025 Approved ALEXANDER HANDY
Interior/Exterior Lathing 11/5/2025 Partial Approval HENRY KIM
BUILDING-Rough-Frame 11/12/2025 Approved JEFFREY HARTLINE
Green Building Rough 11/12/2025 Approved JEFFREY HARTLINE
Insulation 11/12/2025 Not Ready for Inspection JEFFREY HARTLINE
Insulation 11/14/2025 Approved ALEXANDER HANDY
Drywall Nailing 11/24/2025 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 12/9/2025 Approved KRISTEN CAUSEY
Shower Pan 12/9/2025 Approved KRISTEN CAUSEY
Final 12/30/2025 Corrections Issued ROBERT GOLD
Green Building Final 12/30/2025 Not Ready for Inspection ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 12/30/2025 SGSOV Not Ready ROBERT GOLD
Smoke Detectors 12/30/2025 Not Ready for Inspection ROBERT GOLD
ELECTRICAL-Final 1/12/2026 Approved HENRY KIM
Final 1/12/2026 OK to Issue CofO HENRY KIM
Green Building Final 1/12/2026 Approved HENRY KIM
HVAC-Final 1/12/2026 Approved HENRY KIM
PLUMBING-Final 1/12/2026 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 1/12/2026 SGSOV Approved HENRY KIM
Smoke Detectors 1/12/2026 Approved HENRY KIM
Special/Order Compliance 1/12/2026 Partial Inspection DAVID FASTIGGI