7048-7050 N BOTHWELL ROAD 91335
Certificate Information: 7048-7050 N BOTHWELL ROAD 91335
- Application / Permit
- 25014-20000-01797
- Plan Check / Job No.
- B25VN11307
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATT. GARAGE TO (N) ACCESSORY DWELLING UNIT WITH 2-STORY 20' x 29'-9" ADDITION [PER LAMC 12.22 A.33 (c) and (e)]
- Permit Issued
- Issued on 5/28/2025
- Issuing Office
- Current Status
- CofO Issued on 1/26/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/23/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/24/2025 | SEAN SHAHMIRI |
| Corrections Issued | 5/5/2025 | SEAN SHAHMIRI |
| Quality Review Completed | 5/9/2025 | STEVEN KIM |
| Building Plans Picked Up | 5/12/2025 | APPLICANT |
| Plan Check Approved | 5/23/2025 | SEAN SHAHMIRI |
| Issued | 5/28/2025 | APPLICANT |
| CofO in Progress | 12/18/2025 | ARUTYUN MADATYAN |
| Permit Finaled | 1/26/2026 | JOHN JANSON |
| CofO Issued | 1/26/2026 | JOHN JANSON |
| Permit Finaled | 1/26/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/7/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 5/7/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 5/7/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 5/7/2025 | MICHAEL BROWN |
| ZI | Cleared | 5/16/2025 | JASON CHAN |
Contact Information
| Contractor | La Family Builders Inc ; Lic. No.: 1120579-B | 6355 TOPANGA CANYON BLVD UNIT 331 WOODLAND HIILS, CA 91367 |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/17/2025 | Partial Approval | ARUTYUN MADATYAN |
| Sewer | 6/17/2025 | Approved | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 6/20/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Deputy Drilled-In Anchors | 6/23/2025 | Conditional Approval | ARUTYUN MADATYAN |
| Deputy Drilled-In Anchors | 6/23/2025 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 6/25/2025 | Approved | KRISTEN CAUSEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2025 | Partial Approval | ARUTYUN MADATYAN |
| Pre-Inspection | 7/11/2025 | Partial Inspection | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 8/14/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 8/14/2025 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2025 | Partial Approval | ARUTYUN MADATYAN |
| Green Building Rough | 8/14/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 8/14/2025 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 8/20/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Green Building Rough | 8/20/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| HVAC-Rough | 8/20/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Wood Frame | 8/20/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Deputy Wood Construction | 8/21/2025 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 8/21/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Wood Frame | 8/21/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| HVAC-Rough | 8/27/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Special/Order Compliance | 8/27/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 8/28/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 8/28/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 8/28/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 8/29/2025 | Partial Approval | ARUTYUN MADATYAN |
| Insulation | 9/2/2025 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2025 | Partial Approval | ARUTYUN MADATYAN |
| Drywall Nailing | 9/9/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 10/9/2025 | Partial Approval | ARUTYUN MADATYAN |
| Shower Pan | 10/9/2025 | Approved | ARUTYUN MADATYAN |
| Special/Order Compliance | 10/9/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 11/26/2025 | SGSOV Not Ready | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 12/3/2025 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Final | 12/5/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Service/Power Release | 12/5/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 12/8/2025 | Approved | JUAN ALVARADO |
| Final | 12/8/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Green Building Final | 12/8/2025 | Approved | JUAN ALVARADO |
| HVAC-Final | 12/8/2025 | Not Ready for Inspection | JUAN ALVARADO |
| PLUMBING-Final | 12/8/2025 | Approved | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 12/8/2025 | SGSOV Approved | JUAN ALVARADO |
| Smoke Detectors | 12/8/2025 | Approved | JUAN ALVARADO |
| Final | 12/12/2025 | No Access for Inspection | ARUTYUN MADATYAN |
| HVAC-Final | 12/12/2025 | No Access for Inspection | ARUTYUN MADATYAN |
| Final | 12/18/2025 | OK to Issue CofO | ARUTYUN MADATYAN |
| HVAC-Final | 12/18/2025 | Approved | ARUTYUN MADATYAN |
| Service/Power Release | 12/18/2025 | Approved | ARUTYUN MADATYAN |