11330 W BLIX ST 91602
Certificate Information: 11330 W BLIX ST 91602
- Application / Permit
- 25014-20000-01787
- Plan Check / Job No.
- B25VN11266
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan (N) ADDITION AT REAR AND ENCLOSE (E) FRONT PORCH AS PART OF SFD. INTERIOR REMODEL TO CONVERT LAUNDRY AREA TO BATHROOM.
- Permit Issued
- Issued on 5/19/2025
- Issuing Office
- Current Status
- CofO Issued on 9/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/23/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2025 | ALEC MOUSAKHANIAN |
| Corrections Issued | 4/26/2025 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 5/15/2025 | ISIS ARGUETA |
| Issued | 5/19/2025 | APPLICANT |
| CofO in Progress | 9/10/2025 | JAVIER RAMOS JR |
| Permit Finaled | 9/19/2025 | RUBEN SALAS |
| CofO Issued | 9/19/2025 | RUBEN SALAS |
| Permit Finaled | 9/19/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 5/13/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/5/2025 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 6/13/2025 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2025 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 6/25/2025 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 6/25/2025 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 7/16/2025 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 7/16/2025 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2025 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 7/16/2025 | Approved | JAVIER RAMOS JR |
| MERV13>=Rough | 7/16/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 7/16/2025 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 7/22/2025 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 7/22/2025 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 7/22/2025 | Approved | JAVIER RAMOS JR |
| Shower Pan | 7/22/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 9/4/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 9/4/2025 | Approved | JAVIER RAMOS JR |
| Final | 9/4/2025 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 9/4/2025 | Approved | JAVIER RAMOS JR |
| Green Building Final | 9/4/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 9/4/2025 | Approved | JAVIER RAMOS JR |
| MERV13>=Final | 9/4/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 9/4/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 9/4/2025 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 9/4/2025 | Approved | JAVIER RAMOS JR |
| Final | 9/9/2025 | OK to Issue CofO | JAVIER RAMOS JR |
| Pre-Inspection | 9/9/2025 | Approved | JAVIER RAMOS JR |