19858 W SUPERIOR ST 91311
Certificate Information: 19858 W SUPERIOR ST 91311
- Application / Permit
- 25014-20000-01779
- Plan Check / Job No.
- B25VN11218
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- ADDITION TO FIRST AND SECOND FLOORS AS WELL AS AN INTERIOR REMODEL
- Permit Issued
- Issued on 9/8/2025
- Issuing Office
- Current Status
- Issued on 9/8/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/24/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/1/2025 | ARSALAN SHABESTARI |
| Corrections Issued | 5/7/2025 | ARSALAN SHABESTARI |
| Quality Review Completed | 5/20/2025 | GARO TELMI |
| Applicant returned to address corrections | 7/6/2025 | ARSALAN SHABESTARI |
| Plan Check Approved | 9/6/2025 | ARSALAN SHABESTARI |
| Issued | 9/8/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/25/2025 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/29/2025 | TREVOR QUAN |
| Sewer availability | Cleared | 5/29/2025 | TREVOR QUAN |
Contact Information
| Contractor | R L Remodeling Inc; Lic. No.: 885032-B | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/25/2025 | Conditional Approval | HENRY KIM |
| Excavation/Setback/Form/Re-Bar | 9/30/2025 | Approved | DAVID SCANTLIN |
| Footing/Foundation/Slab | 9/30/2025 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2025 | Partial Approval | KRISTEN CAUSEY |
| PLUMBING-Rough | 10/14/2025 | Corrections Issued | KRISTEN CAUSEY |
| PLUMBING-Rough | 10/15/2025 | Partial Approval | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2025 | Partial Approval | KRISTEN CAUSEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2025 | Partial Approval | KRISTEN CAUSEY |
| Deputy Wood Construction | 12/1/2025 | Conditional Approval | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2025 | Partial Approval | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 12/3/2025 | Corrections Issued | DAVID SCANTLIN |
| ELECTRICAL-Rough | 12/3/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| PLUMBING-Rough | 12/3/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| ELECTRICAL-Rough | 12/4/2025 | Approved | KRISTEN CAUSEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2025 | Approved | KRISTEN CAUSEY |
| PLUMBING-Rough | 12/4/2025 | Approved | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 12/19/2025 | Approved | DAVID SCANTLIN |
| Green Building Rough | 12/19/2025 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 12/19/2025 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 12/19/2025 | Partial Approval | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/2/2026 | Partial Inspection | KRISTEN CAUSEY |
| Insulation | 1/2/2026 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 1/2/2026 | Approved | KRISTEN CAUSEY |
| Drywall Nailing | 1/6/2026 | Approved | TROY SANDERS |
| Green Building Final | 3/20/2026 | Not Ready for Inspection | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 3/20/2026 | SGSOV Not Ready | JACK KARGODORIAN |
| Smoke Detectors | 3/20/2026 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 3/24/2026 | Corrections Issued | JACK KARGODORIAN |
| Final | 6/3/2026 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 6/3/2026 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 6/3/2026 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 6/3/2026 | Approved | JACK KARGODORIAN |