5246-5248 N ALLOTT AVE 91401

Certificate Information: 5246-5248 N ALLOTT AVE 91401

Application / Permit
25014-20000-01775
Plan Check / Job No.
B25VN11174
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE (E) 1524 SF SFD EXCEPT FOR 1'-6" OF WALL AND FOUNDATION TO REMAIN. REBUILD 42'-4" X 73' IRREGULAR SHAPED 2-STORY SFD W/ ACCESSORY DWELLING UNIT PER GC 66323(a)(1) AND 2-CAR GARAGE AND TRELLIS PATIO. NPFA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 6/17/2025
Issuing Office
Current Status
CofO Issued on 7/7/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/22/2025 APPLICANT
Assigned to Plan Check Engineer 4/24/2025 RAPHAEL ROSAS
Corrections Issued 4/28/2025 RAPHAEL ROSAS
Quality Review Completed 4/30/2025 STEVEN KIM
Building Plans Picked Up 4/30/2025 APPLICANT
Applicant returned to address corrections 6/5/2025 RAPHAEL ROSAS
Plan Check Approved 6/11/2025 RAPHAEL ROSAS
Issued 6/17/2025 APPLICANT
CofO in Progress 5/19/2026 VINCENT HANLEY
CofO Issued 7/7/2026 RUBEN SALAS
Permit Finaled 7/7/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/30/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 4/30/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 5/5/2025 BIAINA HARITUNIAN
Sewer availability Cleared 5/20/2025 BIAINA HARITUNIAN
Trees in Parkway Cleared 5/21/2025 MIGUEL ORNELAS
Permit Cleared 5/22/2025 BIAINA HARITUNIAN

Contact Information

Contractor Gt Remodeling Inc; Lic. No.: 1091310-B 15250 VENTURA BLVD      SHERMAN OAKS, CA 91403
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/9/2025 Approved NICHOLAS TROWBRIDGE
Sewer 7/17/2025 Partial Inspection MISAEL ESPARZA
PLUMBING-Rough 7/23/2025 Approved KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 7/28/2025 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 7/28/2025 Not Ready for Inspection MISAEL ESPARZA
Grounding or Bonding 7/28/2025 Partial Inspection MISAEL ESPARZA
Deputy Steel/Welding 8/15/2025 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 8/21/2025 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 9/2/2025 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 9/11/2025 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 9/30/2025 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 10/7/2025 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/9/2025 Partial Inspection MISAEL ESPARZA
HVAC-Rough 10/14/2025 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/15/2025 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/21/2025 Corrections Issued MISAEL ESPARZA
Deputy Wood Construction 10/27/2025 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 10/30/2025 Corrections Issued MISAEL ESPARZA
HVAC-Rough 10/30/2025 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 11/5/2025 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 11/19/2025 Approved MISAEL ESPARZA
Shower Pan 11/19/2025 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 11/21/2025 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 11/21/2025 Corrections Issued MISAEL ESPARZA
Green Building Rough 11/21/2025 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 11/26/2025 Approved MISAEL ESPARZA
ELECTRICAL-Rough 11/26/2025 Approved MISAEL ESPARZA
Interior/Exterior Lathing 12/8/2025 Partial Approval MISAEL ESPARZA
Insulation 12/17/2025 Approved MISAEL ESPARZA
Drywall Nailing 12/22/2025 Partial Inspection MISAEL ESPARZA
Interior/Exterior Lathing 12/22/2025 Approved MISAEL ESPARZA
Drywall Nailing 12/30/2025 Approved MICHAEL CORTEZ
Gas Test 5/12/2026 Partial Approval MISAEL ESPARZA
HVAC-Final 5/14/2026 Approved GAREN HAYRAPETYAN
ELECTRICAL-Final 5/15/2026 Approved VINCENT HANLEY
Final 5/15/2026 OK to Issue CofO VINCENT HANLEY
Green Building Final 5/15/2026 Approved VINCENT HANLEY
HVAC-Final 5/15/2026 Approved VINCENT HANLEY
PLUMBING-Final 5/15/2026 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 5/15/2026 SGSOV Approved VINCENT HANLEY
Service/Power Release 5/15/2026 Approved VINCENT HANLEY
Smoke Detectors 5/15/2026 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 5/15/2026 Approved VINCENT HANLEY