16506 W MAYALL ST 91343

Certificate Information: 16506 W MAYALL ST 91343

Application / Permit
25014-20000-01740
Plan Check / Job No.
B25VN10954
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. Convert (E) detached garage into an ADU and addition to ADU to build a 931 sf ADU. Per LAMC 12.22 A.33(b)(1)3
Permit Issued
Issued on 6/18/2025
Issuing Office
Current Status
CofO Issued on 6/4/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/21/2025 APPLICANT
Assigned to Plan Check Engineer 4/24/2025 ALFREDO JARA
Corrections Issued 4/25/2025 ALFREDO JARA
Applicant returned to address corrections 6/12/2025 ALFREDO JARA
Plan Check Approved 6/17/2025 ALFREDO JARA
Issued 6/18/2025 APPLICANT
CofO in Progress 5/7/2026 CHRISTOPHER ROJAS
Permit Finaled 6/4/2026 RUBEN SALAS
CofO Issued 6/4/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/14/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 5/15/2025 RYAN CASTRO
Sewer availability Cleared 5/15/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 5/16/2025 BIAINA HARITUNIAN
Construction near power lines Cleared 5/19/2025 ENRIQUE ACOSTA
GPI Written Notices Cleared 6/13/2025 ALFREDO JARA
Grading Pre-Inspection Cleared 12/30/2025 MANUEL TEJADA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/29/2025 Partial Approval CHRISTOPHER ROJAS
Special/Order Compliance 10/29/2025 Corrections Issued CHRISTOPHER ROJAS
Underground Mechanical 10/29/2025 Approved CHRISTOPHER ROJAS
Footing/Foundation/Slab 11/7/2025 Conditional Approval CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 12/4/2025 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 12/31/2025 Approved KEVIN BERBERYAN
Green Building Rough 12/31/2025 Not Ready for Inspection KEVIN BERBERYAN
Rough-Elec/Plmb/HVAC 12/31/2025 Corrections Issued KEVIN BERBERYAN
BUILDING-Rough-Frame 1/9/2026 Approved ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 1/9/2026 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 1/9/2026 Approved ROBERTO PALACIOS-LOPEZ
Insulation 1/9/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Rough-Elec/Plmb/HVAC 1/9/2026 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 1/13/2026 Approved MICHAEL CORTEZ
Drywall Nailing 1/15/2026 Approved CHRISTOPHER ROJAS
Insulation 1/15/2026 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 1/15/2026 Partial Approval CHRISTOPHER ROJAS
Shower Pan 1/23/2026 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 1/28/2026 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 4/27/2026 Corrections Issued CHRISTOPHER ROJAS
Final 4/27/2026 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 4/27/2026 Approved CHRISTOPHER ROJAS
PLUMBING-Final 4/27/2026 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 4/27/2026 SGSOV Not Ready CHRISTOPHER ROJAS
Smoke Detectors 4/27/2026 Approved CHRISTOPHER ROJAS
Final 5/4/2026 OK to Issue CofO CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 5/4/2026 SGSOV Approved CHRISTOPHER ROJAS