16506 W MAYALL ST 91343
Certificate Information: 16506 W MAYALL ST 91343
- Application / Permit
- 25014-20000-01740
- Plan Check / Job No.
- B25VN10954
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. Convert (E) detached garage into an ADU and addition to ADU to build a 931 sf ADU. Per LAMC 12.22 A.33(b)(1)3
- Permit Issued
- Issued on 6/18/2025
- Issuing Office
- Current Status
- CofO Issued on 6/4/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/21/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/24/2025 | ALFREDO JARA |
| Corrections Issued | 4/25/2025 | ALFREDO JARA |
| Applicant returned to address corrections | 6/12/2025 | ALFREDO JARA |
| Plan Check Approved | 6/17/2025 | ALFREDO JARA |
| Issued | 6/18/2025 | APPLICANT |
| CofO in Progress | 5/7/2026 | CHRISTOPHER ROJAS |
| Permit Finaled | 6/4/2026 | RUBEN SALAS |
| CofO Issued | 6/4/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/14/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 5/15/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 5/15/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 5/16/2025 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 5/19/2025 | ENRIQUE ACOSTA |
| GPI Written Notices | Cleared | 6/13/2025 | ALFREDO JARA |
| Grading Pre-Inspection | Cleared | 12/30/2025 | MANUEL TEJADA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/29/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Special/Order Compliance | 10/29/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Underground Mechanical | 10/29/2025 | Approved | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 11/7/2025 | Conditional Approval | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2025 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 12/31/2025 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 12/31/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Rough-Elec/Plmb/HVAC | 12/31/2025 | Corrections Issued | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 1/9/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 1/9/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 1/9/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 1/9/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Rough-Elec/Plmb/HVAC | 1/9/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 1/13/2026 | Approved | MICHAEL CORTEZ |
| Drywall Nailing | 1/15/2026 | Approved | CHRISTOPHER ROJAS |
| Insulation | 1/15/2026 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 1/15/2026 | Partial Approval | CHRISTOPHER ROJAS |
| Shower Pan | 1/23/2026 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 1/28/2026 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 4/27/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 4/27/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 4/27/2026 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Final | 4/27/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 4/27/2026 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Smoke Detectors | 4/27/2026 | Approved | CHRISTOPHER ROJAS |
| Final | 5/4/2026 | OK to Issue CofO | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 5/4/2026 | SGSOV Approved | CHRISTOPHER ROJAS |