8029 N LOUISE AVE 91325

Certificate Information: 8029 N LOUISE AVE 91325

Application / Permit
25014-20000-01717
Plan Check / Job No.
B25VN10771
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMOVE ALL BUT 6 LF OF WALL AND REBUILD 26'-7" X 32'-0" DETACHED ACCESSORY DWELLING UNIT PER GCS 66323(A)(2), ALL WORK PER ENG.
Permit Issued
Issued on 5/7/2025
Issuing Office
Valley
Current Status
CofO Issued on 1/30/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/18/2025 APPLICANT
Assigned to Plan Check Engineer 4/24/2025 JEROME MAGAT PALMA
Corrections Issued 4/24/2025 JEROME MAGAT PALMA
Building Plans Picked Up 4/29/2025 APPLICANT
Plan Check Approved 5/7/2025 LUISANGEL VALENZUELA
Issued 5/7/2025 APPLICANT
CofO in Progress 1/27/2026 GAREN HAYRAPETYAN
Permit Finaled 1/30/2026 RUBEN SALAS
CofO Issued 1/30/2026 RUBEN SALAS
Permit Finaled 1/30/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/3/2025 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 5/3/2025 COLIN LOREDO
Roof/Waste drainage to street Cleared 5/3/2025 COLIN LOREDO
Sewer availability Cleared 5/3/2025 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Ebrahimi,, Amirhosin; Lic. No.: C92049 8619 RESEDA BLVD UNIT 304B      NORTHRIDGE, CA 91324

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/14/2025 Corrections Issued NICHOLAS TROWBRIDGE
PLUMBING-Rough 7/14/2025 Partial Approval NICHOLAS TROWBRIDGE
Footing/Foundation/Slab 7/16/2025 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 7/18/2025 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 7/21/2025 Approved RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 7/24/2025 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 7/28/2025 Partial Approval SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 7/28/2025 Approved SALVADOR MARTINEZ
Special/Order Compliance 7/28/2025 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 9/25/2025 Approved NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 9/25/2025 Partial Approval NICHOLAS TROWBRIDGE
PLUMBING-Rough 9/25/2025 Corrections Issued NICHOLAS TROWBRIDGE
Rough-Elec/Plmb/HVAC 9/25/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Underground Mechanical 9/25/2025 Approved NICHOLAS TROWBRIDGE
Wood Frame 9/25/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
HVAC-Rough 9/30/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 9/30/2025 Approved GAREN HAYRAPETYAN
Wood Frame 9/30/2025 Approved GAREN HAYRAPETYAN
Insulation 10/8/2025 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 10/8/2025 Partial Approval OGANES TARAKHCHYAN
Drywall Nailing 10/15/2025 Approved WAYNE REGESTER
Shower Pan 11/10/2025 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 11/15/2025 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 12/30/2025 Approved GAREN HAYRAPETYAN
Final 12/30/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 12/30/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 12/30/2025 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 12/30/2025 SGSOV Approved GAREN HAYRAPETYAN
Smoke Detectors 12/30/2025 Approved GAREN HAYRAPETYAN
Final 1/20/2026 Not Ready for Inspection NICHOLAS TROWBRIDGE
Final 1/27/2026 OK to Issue CofO GAREN HAYRAPETYAN