8029 N LOUISE AVE 91325
Certificate Information: 8029 N LOUISE AVE 91325
- Application / Permit
- 25014-20000-01717
- Plan Check / Job No.
- B25VN10771
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- REMOVE ALL BUT 6 LF OF WALL AND REBUILD 26'-7" X 32'-0" DETACHED ACCESSORY DWELLING UNIT PER GCS 66323(A)(2), ALL WORK PER ENG.
- Permit Issued
- Issued on 5/7/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/30/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/24/2025 | JEROME MAGAT PALMA |
| Corrections Issued | 4/24/2025 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 4/29/2025 | APPLICANT |
| Plan Check Approved | 5/7/2025 | LUISANGEL VALENZUELA |
| Issued | 5/7/2025 | APPLICANT |
| CofO in Progress | 1/27/2026 | GAREN HAYRAPETYAN |
| Permit Finaled | 1/30/2026 | RUBEN SALAS |
| CofO Issued | 1/30/2026 | RUBEN SALAS |
| Permit Finaled | 1/30/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/3/2025 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 5/3/2025 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 5/3/2025 | COLIN LOREDO |
| Sewer availability | Cleared | 5/3/2025 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ebrahimi,, Amirhosin; Lic. No.: C92049 | 8619 RESEDA BLVD UNIT 304B NORTHRIDGE, CA 91324 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/14/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 7/14/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Footing/Foundation/Slab | 7/16/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 7/18/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 7/21/2025 | Approved | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 7/24/2025 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 7/28/2025 | Partial Approval | SALVADOR MARTINEZ |
| Excavation/Setback/Form/Re-Bar | 7/28/2025 | Approved | SALVADOR MARTINEZ |
| Special/Order Compliance | 7/28/2025 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 9/25/2025 | Approved | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 9/25/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Rough-Elec/Plmb/HVAC | 9/25/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Underground Mechanical | 9/25/2025 | Approved | NICHOLAS TROWBRIDGE |
| Wood Frame | 9/25/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 9/30/2025 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 9/30/2025 | Approved | GAREN HAYRAPETYAN |
| Wood Frame | 9/30/2025 | Approved | GAREN HAYRAPETYAN |
| Insulation | 10/8/2025 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 10/8/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Drywall Nailing | 10/15/2025 | Approved | WAYNE REGESTER |
| Shower Pan | 11/10/2025 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 11/15/2025 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 12/30/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 12/30/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Final | 12/30/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 12/30/2025 | Approved | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 12/30/2025 | SGSOV Approved | GAREN HAYRAPETYAN |
| Smoke Detectors | 12/30/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 1/20/2026 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Final | 1/27/2026 | OK to Issue CofO | GAREN HAYRAPETYAN |