14862 W ENVOY ST 91342
Certificate Information: 14862 W ENVOY ST 91342
- Application / Permit
- 25014-20000-01684
- Plan Check / Job No.
- B25VN10601
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INT REMODEL AND FRONT/REAR ADDITION. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/12/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/23/2025 | ARAMIK SHAHMIRZAIAN |
| Corrections Issued | 4/24/2025 | ARAMIK SHAHMIRZAIAN |
| Building Plans Picked Up | 4/25/2025 | APPLICANT |
| Plan Check Approved | 4/29/2025 | NAREG ATARIAN |
| Issued | 5/12/2025 | APPLICANT |
| CofO in Progress | 8/19/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 9/12/2025 | RUBEN SALAS |
| CofO Issued | 9/12/2025 | RUBEN SALAS |
| Permit Finaled | 9/12/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/28/2025 | ALEXANDER HELFER |
| Eng Process Fee Ord 176,300 | Cleared | 4/29/2025 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 4/29/2025 | COLIN LOREDO |
| Sewer availability | Cleared | 4/29/2025 | COLIN LOREDO |
Contact Information
| Contractor | New Look Construction Inc; Lic. No.: 1098333-B | 7837 LAUREL CANYON BLVD NORTH HOLLYWOOD, CA 91605 |
| Engineer | Valencia,, Byron Steve; Lic. No.: C87372 | 16000 VENTURA BLVD., PH 1203 ENCINO, CA 91436 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/20/2025 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 5/21/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 5/21/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 5/21/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Rough-Elec/Plmb/HVAC | 5/21/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Underground Mechanical | 5/21/2025 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 5/30/2025 | Approved | JENNIFER RABUCHIN |
| Gas Test | 5/30/2025 | Partial Approval | JENNIFER RABUCHIN |
| HVAC-Rough | 5/30/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 5/30/2025 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/30/2025 | Approved | JENNIFER RABUCHIN |
| Sewer | 5/30/2025 | Approved | JENNIFER RABUCHIN |
| Insulation | 6/3/2025 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 6/3/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Drywall Nailing | 6/6/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 6/6/2025 | Approved | KEVIN BERBERYAN |
| Shower Pan | 6/6/2025 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 8/18/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 8/18/2025 | Approved | JENNIFER RABUCHIN |
| Final | 8/18/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 8/18/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 8/18/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 8/18/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 8/18/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 8/18/2025 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 8/18/2025 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 8/18/2025 | Approved | JENNIFER RABUCHIN |