4312 N EMPRESS AVE 91436

Certificate Information: 4312 N EMPRESS AVE 91436

Application / Permit
25014-20000-01663
Plan Check / Job No.
B25VN10428
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL TO 2-STORY SFD, CONVERT PORTION OF (E) ATTACHED GARAGE TO SFD, 1ST FLOOR PATIO COVER TO BE PART OF SFD, AND 2ND FLOOR COVERED BALCONY TO BE PART OF (E) SFD PER ENGINEERING
Permit Issued
Issued on 5/16/2025
Issuing Office
Current Status
Issued on 5/16/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/15/2025 APPLICANT
Assigned to Plan Check Engineer 4/17/2025 ALFRED RAMIREZ
Corrections Issued 4/24/2025 ALFRED RAMIREZ
Quality Review Completed 4/24/2025 STEVEN KIM
Building Plans Picked Up 4/24/2025 APPLICANT
Plan Check Approved 5/16/2025 ALFRED RAMIREZ
Issued 5/16/2025 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 4/29/2025 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 4/29/2025 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 4/29/2025 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 4/29/2025 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 4/29/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/29/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 4/29/2025 LEE GUILBEAUX
Grading Pre-Inspection Cleared 5/2/2025 MANUEL TEJADA

Contact Information

Contractor Owner-Builder       ,
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/12/2025 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 6/16/2025 Corrections Issued JOHN COLEMAN
Excavation/Setback/Form/Re-Bar 6/17/2025 Approved JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 9/19/2025 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 10/15/2025 Partial Approval JOHN KIDWELL
HVAC-Rough 10/16/2025 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 10/16/2025 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/17/2025 Conditional Approval THOMAS FINNILA
PLUMBING-Rough 10/21/2025 Partial Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/23/2025 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 10/31/2025 Conditional Approval THOMAS FINNILA
HVAC-Rough 10/31/2025 Approved THOMAS FINNILA
BUILDING-Rough-Frame 11/6/2025 Corrections Issued THOMAS FINNILA
Green Building Rough 11/6/2025 Approved THOMAS FINNILA
Wood Frame 11/14/2025 Conditional Approval THOMAS FINNILA
Interior/Exterior Lathing 11/19/2025 Approved SEAN WIRCH
Insulation 12/3/2025 Conditional Approval THOMAS FINNILA
Shower Pan 12/3/2025 Approved THOMAS FINNILA
Interior/Exterior Lathing 12/15/2025 Approved THOMAS FINNILA
Drywall Nailing 2/5/2026 Approved THOMAS FINNILA
BUILDING-Rough-Frame 2/11/2026 Approved THOMAS FINNILA
Insulation 2/11/2026 Approved THOMAS FINNILA
ELECTRICAL-Final 6/4/2026 Not Ready for Inspection THOMAS FINNILA
HVAC-Final 6/4/2026 Not Ready for Inspection THOMAS FINNILA