821 S MUIRFIELD ROAD 90005
Certificate Information: 821 S MUIRFIELD ROAD 90005
- Application / Permit
- 25014-20000-01652
- Plan Check / Job No.
- B25VN10351
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) ACCESSORY DWELLING UNIT PER PER LAMC 12.22 A.33(b)(1),(c),(d),(h) and (k). ALL WORK PER WFPP
- Permit Issued
- Issued on 6/20/2025
- Issuing Office
- Current Status
- Issued on 6/20/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/15/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2025 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 4/29/2025 | SEWADA ZADOORIAN MILAGARDI |
| Building Plans Picked Up | 4/29/2025 | APPLICANT |
| Issued | 6/20/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/3/2025 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 5/3/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 5/3/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 5/5/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 5/5/2025 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/10/2025 | Approved | JOSH MEISTER |
| Excavation/Setback/Form/Re-Bar | 8/13/2025 | Corrections Issued | JEFFREY MEAD |
| Footing/Foundation/Slab | 8/13/2025 | Not Ready for Inspection | JEFFREY MEAD |
| METHANE-Barrier | 8/13/2025 | Not Ready for Inspection | JEFFREY MEAD |
| METHANE-Subgrade | 8/13/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 8/19/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Footing/Foundation/Slab | 8/19/2025 | Not Ready for Inspection | JEFFREY MEAD |
| METHANE-Barrier | 8/19/2025 | Approved | JEFFREY MEAD |
| METHANE-Subgrade | 8/19/2025 | Approved | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 8/20/2025 | Conditional Approval | JEFFREY MEAD |
| Footing/Foundation/Slab | 8/20/2025 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 9/10/2025 | Partial Inspection | JEFFREY MEAD |
| Underground Mechanical | 9/10/2025 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2025 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2025 | Corrections Issued | JOSH MEISTER |
| Sewer | 10/24/2025 | Not Ready for Inspection | JOSH MEISTER |
| Sewer | 11/10/2025 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 11/26/2025 | Approved | JEFFREY MEAD |
| METHANE-Rough | 11/26/2025 | Approved | JEFFREY MEAD |
| ELECTRICAL-Rough | 12/29/2025 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2025 | Corrections Issued | JEFFREY MEAD |
| HVAC-Rough | 12/29/2025 | Corrections Issued | JEFFREY MEAD |
| PLUMBING-Rough | 12/29/2025 | Corrections Issued | JEFFREY MEAD |
| BUILDING-Rough-Frame | 1/2/2026 | Approved | BRENDAN MORELLI |
| Gas Test | 1/2/2026 | Partial Approval | BRENDAN MORELLI |
| Green Building Rough | 1/2/2026 | Approved | BRENDAN MORELLI |
| HVAC-Rough | 1/2/2026 | Approved | BRENDAN MORELLI |
| PLUMBING-Rough | 1/2/2026 | Approved | BRENDAN MORELLI |
| Verify Sprinkler Sign Off | 1/2/2026 | Approved | BRENDAN MORELLI |
| Insulation | 1/15/2026 | Approved | RONNIE MINDANAO |
| Shower Pan | 1/15/2026 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 1/26/2026 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 1/26/2026 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 5/6/2026 | Approved | JEFFREY MEAD |
| Final | 5/6/2026 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 5/6/2026 | Approved | JEFFREY MEAD |
| HVAC-Final | 5/6/2026 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 5/6/2026 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 5/6/2026 | SGSOV Approved | JEFFREY MEAD |
| Service/Power Release | 5/6/2026 | Not Ready for Inspection | JEFFREY MEAD |
| Smoke Detectors | 5/6/2026 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Final | 6/17/2026 | Approved | JEFFREY MEAD |
| Final | 6/17/2026 | Partial Inspection | JEFFREY MEAD |
| HVAC-Final | 6/17/2026 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 6/17/2026 | Approved | JEFFREY MEAD |
| Service/Power Release | 6/17/2026 | Approved | JEFFREY MEAD |
| Smoke Detectors | 6/17/2026 | Approved | JEFFREY MEAD |