3843 N RANDOLPH AVE 90032

Certificate Information: 3843 N RANDOLPH AVE 90032

Application / Permit
25014-20000-01646
Plan Check / Job No.
B25VN10300
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT PORCH TO LIVING AREA. (N) ADDITION TO HOUSE. NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT.
Permit Issued
Issued on 7/3/2025
Issuing Office
Current Status
Issued on 7/3/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/15/2025 APPLICANT
Assigned to Plan Check Engineer 4/22/2025 JESSE ARELLANO
Corrections Issued 4/23/2025 JESSE ARELLANO
Building Plans Picked Up 5/12/2025 APPLICANT
Plan Check Approved 7/1/2025 ALEC MOUSAKHANIAN
Issued 7/3/2025 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/16/2025 TREVOR QUAN
Sewer availability Cleared 5/16/2025 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 5/21/2025 TREVOR QUAN
Grading Pre-Inspection Cleared 5/27/2025 MICHAEL TEMPLE
"D" conditions Cleared 6/27/2025 DAVID URITA
"Q" conditions Cleared 6/27/2025 DAVID URITA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/15/2025 Partial Approval BRENDAN MORELLI
Sewer 7/15/2025 Approved BRENDAN MORELLI
Excavation/Setback/Form/Re-Bar 7/16/2025 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 7/16/2025 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 10/1/2025 Partial Approval LILIANA PORTILLO
ELECTRICAL-Rough 10/2/2025 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 10/2/2025 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 10/14/2025 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 10/14/2025 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 10/14/2025 Approved LILIANA PORTILLO
HVAC-Rough 10/14/2025 Corrections Issued LILIANA PORTILLO
Insulation 11/4/2025 Approved GEM DE OCAMPO
Interior/Exterior Lathing 11/4/2025 Approved GEM DE OCAMPO
HVAC-Rough 11/5/2025 Approved GEM DE OCAMPO
Drywall Nailing 11/18/2025 Conditional Approval GEM DE OCAMPO
Interior/Exterior Lathing 12/4/2025 Approved GEM DE OCAMPO
Shower Pan 12/4/2025 Approved GEM DE OCAMPO