3843 N RANDOLPH AVE 90032
Certificate Information: 3843 N RANDOLPH AVE 90032
- Application / Permit
- 25014-20000-01646
- Plan Check / Job No.
- B25VN10300
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT PORCH TO LIVING AREA. (N) ADDITION TO HOUSE. NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT.
- Permit Issued
- Issued on 7/3/2025
- Issuing Office
- Current Status
- Issued on 7/3/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/15/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2025 | JESSE ARELLANO |
| Corrections Issued | 4/23/2025 | JESSE ARELLANO |
| Building Plans Picked Up | 5/12/2025 | APPLICANT |
| Plan Check Approved | 7/1/2025 | ALEC MOUSAKHANIAN |
| Issued | 7/3/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/16/2025 | TREVOR QUAN |
| Sewer availability | Cleared | 5/16/2025 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/21/2025 | TREVOR QUAN |
| Grading Pre-Inspection | Cleared | 5/27/2025 | MICHAEL TEMPLE |
| "D" conditions | Cleared | 6/27/2025 | DAVID URITA |
| "Q" conditions | Cleared | 6/27/2025 | DAVID URITA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/15/2025 | Partial Approval | BRENDAN MORELLI |
| Sewer | 7/15/2025 | Approved | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 7/16/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 7/16/2025 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2025 | Partial Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 10/2/2025 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 10/2/2025 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 10/14/2025 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 10/14/2025 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2025 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 10/14/2025 | Corrections Issued | LILIANA PORTILLO |
| Insulation | 11/4/2025 | Approved | GEM DE OCAMPO |
| Interior/Exterior Lathing | 11/4/2025 | Approved | GEM DE OCAMPO |
| HVAC-Rough | 11/5/2025 | Approved | GEM DE OCAMPO |
| Drywall Nailing | 11/18/2025 | Conditional Approval | GEM DE OCAMPO |
| Interior/Exterior Lathing | 12/4/2025 | Approved | GEM DE OCAMPO |
| Shower Pan | 12/4/2025 | Approved | GEM DE OCAMPO |