7965 N LLOYD AVE 91605
Certificate Information: 7965 N LLOYD AVE 91605
- Application / Permit
- 25014-20000-01618
- Plan Check / Job No.
- B25VN10169
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: NEW 28' X 8' ADDITION TO (E) SFD. INTERIOR REMODEL. PER ENGINEER DESIGN.
- Permit Issued
- Issued on 6/16/2025
- Issuing Office
- Current Status
- CofO in Progress on 5/28/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/19/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/23/2025 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 4/24/2025 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 6/11/2025 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 6/14/2025 | MIROOSH KHACHATOORIAN |
| Issued | 6/16/2025 | APPLICANT |
| CofO in Progress | 5/28/2026 | OGANES TARAKHCHYAN |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/28/2025 | BRYAN GODINEZ |
| ZA Case | Cleared | 4/28/2025 | JASON CHAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/2/2025 | BRYAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hernandez, Sotomayor, Daniel; Lic. No.: C93095 | 15755 SATICOY ST APT#306 VAN NUYS, CA 91406 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/26/2025 | Approved | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 8/6/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 8/11/2025 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 8/11/2025 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 9/10/2025 | Partial Approval | VINCENT HANLEY |
| Insulation | 9/10/2025 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 9/10/2025 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2025 | Partial Approval | DAVID MATSON |
| Deputy Wood Construction | 10/23/2025 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2025 | Partial Approval | JACK KARGODORIAN |
| Wood Frame | 11/19/2025 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 12/18/2025 | Corrections Issued | VINCENT HANLEY |
| HVAC-Rough | 12/18/2025 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 12/18/2025 | Approved | VINCENT HANLEY |
| Service/Power Release | 12/18/2025 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 12/24/2025 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 12/26/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 12/26/2025 | Approved | VINCENT HANLEY |
| Green Building Rough | 12/26/2025 | Approved | VINCENT HANLEY |
| HVAC-Rough | 12/26/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 12/26/2025 | Approved | VINCENT HANLEY |
| Insulation | 1/2/2026 | Approved | VINCENT HANLEY |
| Drywall Nailing | 1/28/2026 | Approved | VINCENT HANLEY |
| Shower Pan | 1/28/2026 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 2/5/2026 | Approved | VINCENT HANLEY |
| Final | 5/26/2026 | OK to Issue CofO | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 5/26/2026 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 5/26/2026 | Approved | OGANES TARAKHCHYAN |