5930 N TOPEKA DR 91356
Certificate Information: 5930 N TOPEKA DR 91356
- Application / Permit
- 25014-20000-01601
- Plan Check / Job No.
- B25VN10034
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE (E) 1072 SF SFD EXCEPT FOR 1'-8" OF WALL AND FOUNDATION TO REMAIN ON THE NORTHERN PORTION. REBUILD 35' X 63' 2-STORY IRREGULAR SHAPED SFD W/ 2-CAR GARAGE. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/30/2025
- Issuing Office
- Current Status
- Issued on 5/30/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/11/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/17/2025 | RAPHAEL ROSAS |
| Corrections Issued | 4/22/2025 | RAPHAEL ROSAS |
| Quality Review Completed | 4/24/2025 | STEVEN KIM |
| Building Plans Picked Up | 4/25/2025 | APPLICANT |
| Plan Check Approved | 5/22/2025 | RAPHAEL ROSAS |
| Issued | 5/30/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 4/22/2025 | BIAINA HARITUNIAN |
| Low Impact Development (LID) | Cleared | 4/25/2025 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 5/5/2025 | BIAINA HARITUNIAN |
| Permit | Cleared | 5/13/2025 | BIAINA HARITUNIAN |
| Trees in Parkway | Cleared | 5/13/2025 | MIGUEL ORNELAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/23/2025 | Partial Inspection | MORRIS JACKSON |
| Excavation/Setback/Form/Re-Bar | 7/31/2025 | Approved | MORRIS JACKSON |
| PLUMBING-Rough | 8/4/2025 | Partial Approval | MORRIS JACKSON |
| PLUMBING-Rough | 8/5/2025 | Partial Approval | MORRIS JACKSON |
| Footing/Foundation/Slab | 8/8/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Excavation/Setback/Form/Re-Bar | 8/13/2025 | Approved | MORRIS JACKSON |
| Footing/Foundation/Slab | 8/13/2025 | Partial Approval | MORRIS JACKSON |
| Excavation/Setback/Form/Re-Bar | 8/14/2025 | Corrections Issued | JON MCHUGH |
| Footing/Foundation/Slab | 8/19/2025 | Approved | MORRIS JACKSON |
| Deputy Drilled-In Anchors | 8/20/2025 | Conditional Approval | MORRIS JACKSON |
| BUILDING-Rough-Frame | 9/16/2025 | Corrections Issued | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2025 | Partial Approval | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2025 | No Access for Inspection | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2025 | Corrections Issued | MORRIS JACKSON |
| ELECTRICAL-Rough | 12/11/2025 | Corrections Issued | MORRIS JACKSON |
| Gas Test | 12/11/2025 | Approved | MORRIS JACKSON |
| HVAC-Rough | 12/11/2025 | Approved | MORRIS JACKSON |
| PLUMBING-Rough | 12/11/2025 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 12/19/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2025 | Partial Approval | MORRIS JACKSON |
| Green Building Rough | 12/19/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Verify Sprinkler Sign Off | 12/19/2025 | Corrections Issued | MORRIS JACKSON |
| Shower Pan | 12/31/2025 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 1/9/2026 | Partial Approval | MORRIS JACKSON |
| Interior/Exterior Lathing | 2/19/2026 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 3/9/2026 | Partial Approval | MORRIS JACKSON |
| Green Building Rough | 3/9/2026 | Approved | MORRIS JACKSON |
| Verify Sprinkler Sign Off | 3/9/2026 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 3/10/2026 | Corrections Issued | MORRIS JACKSON |
| Sewer | 3/17/2026 | Approved | MORRIS JACKSON |
| Underground Mechanical | 3/17/2026 | Approved | MORRIS JACKSON |
| Insulation | 3/27/2026 | Approved | MORRIS JACKSON |
| Drywall Nailing | 4/8/2026 | Approved | MORRIS JACKSON |