10348 N DEBRA AVE 91344
Certificate Information: 10348 N DEBRA AVE 91344
- Application / Permit
- 25014-20000-01595
- Plan Check / Job No.
- B25VN09997
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW REAR ADDITION TO EXISTING SINGLE FAMILY DWELLING AND INTERIOR REMODEL OF SFD. WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 4/29/2025
- Issuing Office
- Current Status
- CofO Issued on 1/20/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/11/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/15/2025 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 4/16/2025 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 4/25/2025 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 4/29/2025 | MADISON O'DELL |
| Issued | 4/29/2025 | APPLICANT |
| CofO in Progress | 1/13/2026 | CHRISTOPHER ROJAS |
| Permit Finaled | 1/20/2026 | RUBEN SALAS |
| CofO Issued | 1/20/2026 | RUBEN SALAS |
| Permit Finaled | 1/20/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/25/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 4/25/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 4/25/2025 | RYAN CASTRO |
| Watercourse | Cleared | 4/25/2025 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Santos,, Michael; Lic. No.: C77657 | 16202 ORION AVE CHINO, CA 91708 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/18/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Deputy Drilled-In Anchors | 6/20/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 6/24/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Excavation/Setback/Form/Re-Bar | 6/24/2025 | Approved | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 6/24/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Wood Frame | 7/9/2025 | Partial Approval | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 7/17/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 7/22/2025 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 7/31/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2025 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 8/11/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 8/11/2025 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 8/11/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 8/20/2025 | Approved | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 8/20/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 8/20/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 8/26/2025 | Approved | CHRISTOPHER ROJAS |
| Rough-Elec/Plmb/HVAC | 8/26/2025 | Approved | CHRISTOPHER ROJAS |
| Insulation | 8/29/2025 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 9/8/2025 | Approved | RYAN SALAZAR |
| Shower Pan | 9/8/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 9/18/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 10/15/2025 | Corrections Issued | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 10/21/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 1/8/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 1/8/2026 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 1/8/2026 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 1/8/2026 | Approved | CHRISTOPHER ROJAS |
| Final | 1/13/2026 | OK to Issue CofO | CHRISTOPHER ROJAS |