13766 W ORO GRANDE ST 91342

Certificate Information: 13766 W ORO GRANDE ST 91342

Application / Permit
25014-20000-01593
Plan Check / Job No.
B25VN09985
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL THE SINGLE FAMILY DWELLING WITH 11'7"X7'0" 1ST FLOOR ADDITION AND 11'11"X24'7" 1ST & 2ND FLOOR ADDITIONS WITH A DECK. (NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT)
Permit Issued
Issued on 5/21/2025
Issuing Office
Current Status
Issued on 5/21/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/11/2025 APPLICANT
Assigned to Plan Check Engineer 5/1/2025 MARVEL DELACRUZ
Corrections Issued 5/8/2025 MARVEL DELACRUZ
Quality Review Completed 5/14/2025 JASON HEALEY
Building Plans Picked Up 5/15/2025 APPLICANT
Applicant returned to address corrections 5/21/2025 MARVEL DELACRUZ
Plan Check Approved 5/21/2025 MARVEL DELACRUZ
Issued 5/21/2025 APPLICANT

Permit Application Clearance Information

Miscellaneous Cleared 5/8/2025 JASON CHAN
Roof/Waste drainage to street Cleared 5/11/2025 BRYAN GODINEZ
Sewer availability Cleared 5/11/2025 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 5/16/2025 BRYAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/17/2025 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 6/23/2025 Corrections Issued KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 6/25/2025 Approved KEVIN BERBERYAN
PLUMBING-Rough 6/26/2025 Partial Approval KEVIN BERBERYAN
PLUMBING-Rough 8/21/2025 Approved KEVIN BERBERYAN
ELECTRICAL-Rough 9/2/2025 Approved KEVIN BERBERYAN
HVAC-Rough 9/30/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 10/9/2025 Approved KEVIN BERBERYAN
Wood Frame 10/9/2025 Partial Approval KEVIN BERBERYAN
Insulation 10/16/2025 Approved KEVIN BERBERYAN
Shower Pan 10/16/2025 Approved KEVIN BERBERYAN
Drywall Nailing 10/23/2025 Approved KEVIN BERBERYAN
Green Building Rough 10/23/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 10/27/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 2/10/2026 Approved KEVIN BERBERYAN