831 N TEAKWOOD ROAD 90049
Certificate Information: 831 N TEAKWOOD ROAD 90049
- Application / Permit
- 25014-20000-01589
- Plan Check / Job No.
- B25VN09965
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 74'-6" X 31'-2" IRREGULAR SHAPED ADDITION TO EXISTING SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 5/6/2025
- Issuing Office
- Current Status
- CofO Issued on 6/11/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/10/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/17/2025 | SELLA BENYAMIN |
| Corrections Issued | 4/22/2025 | SELLA BENYAMIN |
| Quality Review Completed | 4/24/2025 | STEVEN KIM |
| Building Plans Picked Up | 4/24/2025 | APPLICANT |
| Plan Check Approved | 5/6/2025 | SELLA BENYAMIN |
| Issued | 5/6/2025 | APPLICANT |
| CofO in Progress | 6/2/2026 | KEVIN SARGSYAN |
| Permit Finaled | 6/11/2026 | RICHARD STEINBACH |
| CofO Issued | 6/11/2026 | RICHARD STEINBACH |
| Permit Finaled | 6/11/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 4/28/2025 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 4/28/2025 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 4/28/2025 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 4/28/2025 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 4/28/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 4/28/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 4/29/2025 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/13/2025 | Corrections Issued | KEVIN SARGSYAN |
| Underground Mechanical | 6/20/2025 | Approved | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 6/27/2025 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2025 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 9/17/2025 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2025 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 9/17/2025 | Partial Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 9/18/2025 | Conditional Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 9/19/2025 | No Access for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 10/1/2025 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2025 | Approved | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 10/1/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Rough | 10/1/2025 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 10/1/2025 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 10/14/2025 | Partial Approval | KEVIN SARGSYAN |
| Shower Pan | 10/14/2025 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 10/15/2025 | Corrections Issued | KEVIN SARGSYAN |
| FLOOD-Proofing Certificate | 10/15/2025 | Approved | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 10/15/2025 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 10/15/2025 | Approved | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 10/15/2025 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 10/22/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| Shower Pan | 10/22/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 10/23/2025 | Approved | KEVIN SARGSYAN |
| Shower Pan | 10/23/2025 | Approved | KEVIN SARGSYAN |
| Insulation | 10/28/2025 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 11/3/2025 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 11/6/2025 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 5/20/2026 | Corrections Issued | KEVIN SARGSYAN |
| Final | 5/20/2026 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Final | 5/20/2026 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 5/20/2026 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Final | 5/20/2026 | Corrections Issued | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 5/20/2026 | SGSOV Not Ready | KEVIN SARGSYAN |
| Service/Power Release | 5/20/2026 | Not Ready for Inspection | KEVIN SARGSYAN |
| Smoke Detectors | 5/20/2026 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 5/27/2026 | Approved | KEVIN SARGSYAN |
| Final | 5/27/2026 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Final | 5/27/2026 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 5/27/2026 | Not Ready for Inspection | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 5/27/2026 | SGSOV Not Ready | KEVIN SARGSYAN |
| Service/Power Release | 5/27/2026 | Approved | KEVIN SARGSYAN |
| Final | 6/2/2026 | OK to Issue CofO | KEVIN SARGSYAN |
| PLUMBING-Final | 6/2/2026 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 6/2/2026 | SGSOV Approved | KEVIN SARGSYAN |