10640 N LANGMUIR AVE 91040

Certificate Information: 10640 N LANGMUIR AVE 91040

Application / Permit
25014-20000-01565
Plan Check / Job No.
B25VN09695
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO AN ACCESSORY DWELLING UNIT WITH ADDITION PER GCS 66323(a)(2).
Permit Issued
Issued on 5/21/2025
Issuing Office
Valley
Current Status
CofO Issued on 7/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/9/2025 APPLICANT
Assigned to Plan Check Engineer 4/15/2025 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 4/18/2025 SEWADA ZADOORIAN MILAGARDI
Building Plans Picked Up 4/18/2025 APPLICANT
Plan Check Approved 5/16/2025 GIOVANNY CHAVEZ
Issued 5/21/2025 APPLICANT
CofO in Progress 6/18/2026 NICHOLAS TROWBRIDGE
Permit Finaled 7/9/2026 RUBEN SALAS
CofO Issued 7/9/2026 RUBEN SALAS
Permit Finaled 7/9/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/26/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 4/26/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 4/28/2025 SAFA JAVANMARDI
Sewer availability Cleared 4/28/2025 SAFA JAVANMARDI
GPI Written Notices Cleared 5/16/2025 SEWADA ZADOORAN MILAGARDI
Grading Pre-Inspection Cleared 5/16/2025 SEWADA ZADOORAN MILAGARDI

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/1/2025 Partial Inspection WILLIAM WREN
Deputy Drilled-In Anchors 10/10/2025 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 10/20/2025 Approved WILLIAM WREN
Underground Mechanical 10/20/2025 Approved WILLIAM WREN
BUILDING-Rough-Frame 12/10/2025 Corrections Issued NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 12/10/2025 Corrections Issued NICHOLAS TROWBRIDGE
Green Building Rough 12/10/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
HVAC-Rough 12/10/2025 Corrections Issued NICHOLAS TROWBRIDGE
PLUMBING-Rough 12/10/2025 Approved NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 12/15/2025 Partial Approval NICHOLAS TROWBRIDGE
Green Building Rough 12/15/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 1/14/2026 Approved NICHOLAS TROWBRIDGE
Deputy Wood Construction 1/14/2026 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 1/14/2026 Approved NICHOLAS TROWBRIDGE
Green Building Rough 1/14/2026 Not Ready for Inspection NICHOLAS TROWBRIDGE
Insulation 1/14/2026 Approved NICHOLAS TROWBRIDGE
Drywall Nailing 1/28/2026 Approved NICHOLAS TROWBRIDGE
Green Building Rough 1/28/2026 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 1/28/2026 Partial Approval NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 2/24/2026 Partial Approval NICHOLAS TROWBRIDGE
Shower Pan 2/24/2026 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 2/27/2026 Approved MATTHEW NELSON
Final 4/13/2026 Corrections Issued NICHOLAS TROWBRIDGE
Footing/Foundation/Slab 4/13/2026 Approved NICHOLAS TROWBRIDGE
Green Building Final 4/13/2026 Not Ready for Inspection NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 4/13/2026 SGSOV Approved NICHOLAS TROWBRIDGE
Smoke Detectors 4/13/2026 Approved NICHOLAS TROWBRIDGE
Final 6/17/2026 OK to Issue CofO NICHOLAS TROWBRIDGE
Green Building Final 6/17/2026 Approved NICHOLAS TROWBRIDGE
Service/Power Release 6/17/2026 Approved NICHOLAS TROWBRIDGE