8148-8152 N GEYSER AVE 91335

Certificate Information: 8148-8152 N GEYSER AVE 91335

Application / Permit
25014-20000-01544
Plan Check / Job No.
B25VN09577
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT 14' X 16'-4' PORTION OF SFD TO ADU AND ADD 30'-2" X 30'-11" TO ENLARGE ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c), (d), and (g) AND LAMC 12.22 A.33(c) and (e); ADD 10'X 24' COVERED PATIO; CONVERT AND ADD TO GARAGE TO BECOME NEW DWELLING UNIT PER SB9 (1267 SQ FT TOTAL); CONVERT 26 SQ FT OF GARAGE TO EXISTING SFD; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 5/13/2025
Issuing Office
Current Status
Issued on 5/13/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/8/2025 APPLICANT
Assigned to Plan Check Engineer 4/10/2025 SELLA BENYAMIN
Corrections Issued 4/15/2025 SELLA BENYAMIN
Quality Review Completed 4/17/2025 STEVEN KIM
Building Plans Picked Up 4/22/2025 APPLICANT
Plan Check Approved 5/13/2025 SELLA BENYAMIN
Issued 5/13/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/30/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 5/1/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 5/1/2025 BIAINA HARITUNIAN
Senate Bill 9 Cleared 5/1/2025 DALIA MOKAYED
Sewer availability Cleared 5/1/2025 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/31/2025 Not Ready for Inspection JUAN ALVARADO
Underground Mechanical 8/14/2025 Partial Approval JUAN ALVARADO
Special/Order Compliance 8/15/2025 Corrections Issued JUAN ALVARADO
Underground Mechanical 8/22/2025 Approved JUAN ALVARADO
Underground Mechanical 12/9/2025 Approved JUAN ALVARADO
Footing/Foundation/Slab 12/18/2025 Corrections Issued JUAN ALVARADO
Deputy Drilled-In Anchors 12/19/2025 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 1/13/2026 Approved ARUTYUN MADATYAN
Wood Frame 1/15/2026 Partial Approval ARUTYUN MADATYAN
Wood Frame 1/16/2026 Not Ready for Inspection ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 1/21/2026 Partial Approval TROY SANDERS
Wood Frame 1/21/2026 Partial Approval TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 2/2/2026 Not Ready for Inspection ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 2/23/2026 Approved JUAN ALVARADO
ELECTRICAL-Rough 3/16/2026 Corrections Issued JUAN ALVARADO
HVAC-Rough 3/16/2026 Corrections Issued JUAN ALVARADO
PLUMBING-Rough 3/16/2026 Corrections Issued JUAN ALVARADO
Interior/Exterior Lathing 3/26/2026 Partial Approval JEFFREY HARTLINE
Rough-Elec/Plmb/HVAC 3/26/2026 Partial Approval JEFFREY HARTLINE
BUILDING-Rough-Frame 3/31/2026 Approved JUAN ALVARADO
ELECTRICAL-Rough 3/31/2026 Approved JUAN ALVARADO
Green Building Rough 3/31/2026 Approved JUAN ALVARADO
Verify Sprinkler Sign Off 3/31/2026 Approved JUAN ALVARADO
Insulation 4/6/2026 Approved JUAN ALVARADO
Drywall Nailing 4/29/2026 Approved JUAN ALVARADO
Shower Pan 4/29/2026 Approved JUAN ALVARADO
Interior/Exterior Lathing 5/8/2026 Approved JUAN ALVARADO