4925 N LEDGE AVE 91601
Certificate Information: 4925 N LEDGE AVE 91601
- Application / Permit
- 25014-20000-01537
- Plan Check / Job No.
- B25VN09526
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE BUILDING EXCEPT FOR 16'-8" OF WALL/FOUNDATION ON EAST SIDE OF LOT; ADD NEW 69'-2" X 44' TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 6/24/2025
- Issuing Office
- Current Status
- Issued on 6/24/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/10/2025 | SELLA BENYAMIN |
| Corrections Issued | 4/15/2025 | SELLA BENYAMIN |
| Quality Review Completed | 4/15/2025 | STEVEN KIM |
| Building Plans Picked Up | 4/18/2025 | APPLICANT |
| Plan Check Approved | 6/17/2025 | SELLA BENYAMIN |
| Issued | 6/24/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/9/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 5/9/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 5/14/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 5/14/2025 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 5/20/2025 | JERRY KAO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 8887 W FALMINGO RD STE 101 LAS VEGAS, NV 89147 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/14/2025 | Corrections Issued | JOSE AVILA |
| Underground Mechanical | 7/14/2025 | Not Ready for Inspection | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 7/16/2025 | Partial Inspection | JOSE AVILA |
| PLUMBING-Rough | 7/16/2025 | Partial Approval | JOSE AVILA |
| Underground Mechanical | 7/16/2025 | Partial Approval | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 7/24/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 7/25/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 8/8/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 8/13/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 8/28/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2025 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Deputy Wood Construction | 9/19/2025 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 10/10/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 10/20/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 10/23/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 10/27/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 10/27/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 11/14/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 11/17/2025 | Partial Inspection | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 11/21/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 11/21/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 11/21/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 12/1/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 12/1/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 12/16/2025 | Approved | LOUIS ESCOTO |
| Shower Pan | 12/19/2025 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Shower Pan | 12/26/2025 | Approved | CHRISTOPHER MORFIN |
| Interior/Exterior Lathing | 1/9/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 3/25/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Grounding or Bonding | 4/28/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Pre-Inspection | 4/28/2026 | Approved | ROBERTO PALACIOS-LOPEZ |