10012 N PLAINVIEW AVE 91042
Certificate Information: 10012 N PLAINVIEW AVE 91042
- Application / Permit
- 25014-20000-01522
- Plan Check / Job No.
- B25VN09438
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 28' 1" x 10' 1" Kitchen, bathroom and closet addition attached to SFD. All work per WFPP.
- Permit Issued
- Issued on 6/10/2025
- Issuing Office
- Current Status
- CofO Issued on 5/11/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2025 | NAREG ATARIAN |
| Corrections Issued | 4/7/2025 | NAREG ATARIAN |
| Applicant returned to address corrections | 6/4/2025 | NAREG ATARIAN |
| Plan Check Approved | 6/10/2025 | ALEC MOUSAKHANIAN |
| Issued | 6/10/2025 | APPLICANT |
| CofO in Progress | 4/21/2026 | DAVID ANDERSON |
| Permit Finaled | 5/11/2026 | RUBEN SALAS |
| CofO Issued | 5/11/2026 | RUBEN SALAS |
| Permit Finaled | 5/11/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2025 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 4/8/2025 | COLIN LOREDO |
| Sewer availability | Cleared | 4/8/2025 | COLIN LOREDO |
| Grading Pre-Inspection | Cleared | 4/14/2025 | MANUEL TEJADA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/8/2025 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 7/11/2025 | Partial Approval | DAVID ANDERSON |
| Footing/Foundation/Slab | 11/14/2025 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 1/30/2026 | Corrections Issued | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2026 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 1/30/2026 | Corrections Issued | DAVID ANDERSON |
| ELECTRICAL-Rough | 2/5/2026 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 2/5/2026 | Partial Approval | DAVID ANDERSON |
| PLUMBING-Rough | 2/5/2026 | Approved | DAVID ANDERSON |
| Sewer | 2/5/2026 | Not Ready for Inspection | DAVID ANDERSON |
| BUILDING-Rough-Frame | 2/9/2026 | Approved | DAVID ANDERSON |
| Green Building Rough | 2/9/2026 | Approved | DAVID ANDERSON |
| HVAC-Rough | 2/9/2026 | Approved | DAVID ANDERSON |
| Insulation | 2/9/2026 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 3/10/2026 | Approved | MICHEL ABAJAN |
| Final | 4/6/2026 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 4/6/2026 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 4/6/2026 | SGSOV Not Ready | DAVID ANDERSON |
| Smoke Detectors | 4/6/2026 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 4/13/2026 | OK to Issue CofO | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 4/13/2026 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 4/13/2026 | Approved | DAVID ANDERSON |