18631-18635 W KNAPP ST 91324

Certificate Information: 18631-18635 W KNAPP ST 91324

Application / Permit
25014-20000-01515
Plan Check / Job No.
B25VN09374
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan: Convert attached garage to JADU per GC 66323(a)(1) and 66333 . All per engineering calcs
Permit Issued
Issued on 6/27/2025
Issuing Office
Current Status
CofO Issued on 10/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/7/2025 APPLICANT
Assigned to Plan Check Engineer 4/10/2025 DAVID CASTILLO
Corrections Issued 4/10/2025 DAVID CASTILLO
Applicant returned to address corrections 5/30/2025 DAVID CASTILLO
Applicant returned to address corrections 6/12/2025 KAVIAN REFAHI
Plan Check Approved 6/26/2025 DAVID CASTILLO
Issued 6/27/2025 APPLICANT
CofO in Progress 10/15/2025 KRISTEN CAUSEY
CofO in Progress 10/15/2025 KRISTEN CAUSEY
CofO in Progress 10/20/2025 KRISTEN CAUSEY
Permit Finaled 10/20/2025 JOHN JANSON
CofO Issued 10/20/2025 JOHN JANSON
Permit Finaled 10/20/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/14/2025 KEVIN CHUNG
Eng Process Fee Ord 176,300 Cleared 5/14/2025 KEVIN CHUNG
Sewer availability Cleared 5/14/2025 KEVIN CHUNG

Contact Information

Contractor Owner-Builder       ,
Engineer Mniarji,, Majd Sameer; Lic. No.: NA93049       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/2/2025 Partial Inspection KRISTEN CAUSEY
Excavation/Setback/Form/Re-Bar 7/14/2025 Approved DAVID SCANTLIN
Footing/Foundation/Slab 7/14/2025 Approved DAVID SCANTLIN
PLUMBING-Rough 7/14/2025 Partial Approval DAVID SCANTLIN
ELECTRICAL-Rough 8/4/2025 Approved KRISTEN CAUSEY
PLUMBING-Rough 8/4/2025 Approved KRISTEN CAUSEY
Wood Frame 8/4/2025 Approved KRISTEN CAUSEY
HVAC-Rough 8/11/2025 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 8/11/2025 Approved KRISTEN CAUSEY
Insulation 8/13/2025 Approved KRISTEN CAUSEY
Drywall Nailing 8/15/2025 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 9/26/2025 Approved KRISTEN CAUSEY
ELECTRICAL-Final 9/26/2025 Approved KRISTEN CAUSEY
Final 9/26/2025 Corrections Issued KRISTEN CAUSEY
Green Building Final 9/26/2025 Approved KRISTEN CAUSEY
Green Building Rough 9/26/2025 Approved KRISTEN CAUSEY
HVAC-Final 9/26/2025 Approved KRISTEN CAUSEY
PLUMBING-Final 9/26/2025 Approved KRISTEN CAUSEY
SGSOV-Seismic Gas S/O Valve 9/26/2025 SGSOV Approved KRISTEN CAUSEY
Smoke Detectors 9/26/2025 Approved KRISTEN CAUSEY
Final 10/14/2025 Corrections Issued KRISTEN CAUSEY
Final 10/20/2025 OK to Issue CofO KRISTEN CAUSEY