10855 N NESTLE AVE 91326

Certificate Information: 10855 N NESTLE AVE 91326

Application / Permit
25014-20000-01496
Plan Check / Job No.
B25VN09176
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
**ePlan** Major alteration and addition to (E) single family dwelling with attached garage, remove (E) breezeway, new attached trellis at front and rear of SFD.
Permit Issued
Issued on 10/10/2025
Issuing Office
Current Status
Issued on 10/10/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/4/2025 APPLICANT
Assigned to Plan Check Engineer 4/17/2025 BEHROUZ KHOKHAR
Corrections Issued 4/22/2025 EDWIN ESPIN
Quality Review Completed 4/22/2025 CHIHARU SUZUKI
Applicant returned to address corrections 8/27/2025 BEHROUZ KHOKHAR
Applicant returned to address corrections 9/24/2025 BEHROUZ KHOKHAR
Plan Check Approved 10/9/2025 BEHROUZ KHOKHAR
Issued 10/10/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/28/2025 JESUS CISNEROS
Sewer availability Cleared 7/28/2025 JESUS CISNEROS
Roof/Waste drainage to street Cleared 8/4/2025 LEE GUILBEAUX

Contact Information

Architect Song,, Michael; Lic. No.: NA32566       ,
Contractor Owner-Builder       ,
Engineer Kazemi,, Milad; Lic. No.: NA92143       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/20/2026 Approved DAVID SCANTLIN
Excavation/Setback/Form/Re-Bar 1/26/2026 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 2/27/2026 Corrections Issued ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 2/27/2026 Not Ready for Inspection ARUTYUN MADATYAN
Green Building Rough 2/27/2026 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 2/27/2026 Partial Approval ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 3/5/2026 Partial Approval DAVID SCANTLIN
Deputy Wood Construction 5/13/2026 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 5/27/2026 Partial Approval JEFFREY HARTLINE
Green Building Rough 5/27/2026 Not Ready for Inspection JEFFREY HARTLINE
Special/Order Compliance 6/17/2026 Approved JACK KARGODORIAN